State Street (US-89) widening
UDOT is widening State Street to a seven-lane section (three lanes each direction) to match the existing sections on either end. The work upgrades signals at 500 East, 700 East, North County Boulevard, 1300 West and Pleasant Grove Boulevard and adds south-side curb, gutter and sidewalk, new storm drain and new or upgraded pedestrian ramps. Phase 1 widened the State Street intersections at 500 East and at Pleasant Grove Boulevard and the 1650 West-1300 West stretch in 2025, plus a new pavement layer between intersections. Phase 2 is in design through 2026, with construction anticipated in 2027 (dates to be determined); 1300 West will be widened in Phase 2.
In review
- Type
- Road project
- Applicant
- UDOT
- Run by
- UDOT
- Location
- State Street, 200 South Pleasant Grove to 500 East American Fork
- Schedule
- Phase 1 completed 2025; Phase 2 design through 2026, construction anticipated 2027
- UDOT project page lists Phase 1 intersections at 500 East and Pleasant Grove Boulevard as complete; Phase 2…
- City Council: Fiscal 2024 budget amendments
- City Council work session: FY2025 water, pressurized irrigation, sewer, storm drain and sanitation funds
- City Council: State of the City address
- City Council: UDOT cooperative agreement on US-89 signals and access (Resolution 2022-01-01R)
In brief
State Street (US-89) widening appears on 5 recorded agendas, from the City Council work session meeting of December 1, 2020 to the City Council meeting of June 25, 2024.
On record, it was approved 2 times.
The most recent decision was approved (4-0) at the City Council meeting of June 25, 2024.
Updates
October 14, 2026
UDOT project page lists Phase 1 intersections at 500 East and Pleasant Grove Boulevard as complete; Phase 2 design ongoing through 2026 with construction anticipated in 2027. Source
Follow the money and project delivery
State Street (US-89) widening
- Council action
In review according to the dated project source. Record → · June 25, 2024
- Money in the record
budget: $2.02 million — State Street 8-inch water pipe replacement, 200 East to 500 East; budget: $1.32 million — Segment 4 18-inch water line, 200 East and 620 South; budget: $770,000 — 300 North Segment III reconstruction water line; budget: $500,000 — Street light capital improvements; budget: $48,637 — Higher recycling and garbage contract fees; budget: $225,000 — Streets loader (trade-in offset) Record → · June 25, 2024
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
June 25, 2024 · City Council
Fiscal 2024 budget amendments
Approved · 4-0
Year-end adjustments. General fund revenue up on sales tax (+$688,841), developer contributions (+$500,000), development inspection (+$300,000) and a $120,000 state police grant; spending added $500,000 for street light capital improvements and $350,000 for development review. Culinary water used $4,230,912 of fund balance: $2,015,000 for State Street 8-inch pipe replacement (200 East to 500 East), $1,319,912 for Segment 4 18-inch line at 200 East and 620 South, $770,000 for the 300 North Segment III reconstruction and $115,000 for non-CDBG-eligible line replacement. PARC tax disbursements approved June 11 total $884,914. Sanitation added $95,899 for higher Republic Services and North Pointe fees. The minutes list the vote but not the motion text.
- Culinary water fund balance used: $4,230,912
- State Street betterments (8-inch pipe, 200 E to 500 E): $2,015,000
- 36-inch water line project, Segment 4 (18-inch line, 200 E & 620 S): $1,319,912
- 300 North Segment III reconstruction water line: $770,000
- Street light capital improvements: $500,000
- General capital: council chambers A/V $50,000; Station 51 water heaters $35,000; park irrigation vaults $72,000; skate park $21,500
- Equipment: streets loader $225,000 (offset by trade-in)
- Republic Services contract fee increases (recycling, cans): ~$48,600
- Broadband fund bad debt write-off: $41,000
March 19, 2024 · City Council work session
FY2025 water, pressurized irrigation, sewer, storm drain and sanitation funds
Discussed
Culinary: no rate increase; $350,000 CDBG Phase 11 grant; 36-inch waterline replacement done in FY2024; continuing 100 East line (500 North to 700 North) and Pacific Drive to 300 North; new State Street main replacement with UDOT betterment (500 East to Pleasant Grove) and Boley well repairs; TOD well about $1 million. PI: $6.6 million state metering grant received the prior year; capital down $6,544,585; $1 million placeholder for TSSD recycled water; PI usage billing expected late 2024 or 2025. Sewer: operations up $1,503,192 (34.9%) on a 16% TSSD increase from Jan. 1, 2024; 450 West/Pacific Drive upsizing pending railroad. Storm drain: 6% rate increase; $350,000 for UDOT betterment bridges at Greenwood/200 South and 400 North/400 East box culverts; $1 million for flood rehabilitation. Sanitation: costs up 11%, about $360,000 reserves; Republic up to 3.5%.
- CDBG grant: $350,000
- PI metering state grant: $6.6 million (prior year)
- Sewer operations: +$1,503,192 (34.9%)
- Storm drain UDOT betterment culverts: $350,000
- Storm water flood rehabilitation: $1 million
- TOD well: about $1 million
- Impact fee revenue assumed down 20%
January 25, 2022 · City Council
State of the City address
No action
Mayor Frost reported 1,180 building permits in 2021, about 30,000 police and 4,772 fire calls, nearly $10 million in grants, $3.4 million in ARPA money aimed at secondary water metering, a fully funded general fund reserve, almost a billion gallons of water saved, about $4.3 million spent on roads, and the purchase of 30 acres south of I-15 with park impact fees for a park and the third fire station. He cited a $43 million regional project to widen State Street into Pleasant Grove.
January 11, 2022 · City Council
UDOT cooperative agreement on US-89 signals and access (Resolution 2022-01-01R)
Approved · 5-0
Approved signal spacing and access control rules along US-89 (State Street).
December 1, 2020 · City Council work session
UDOT update on State Street (US-89) widening
Discussed
UDOT project manager Eric Mason said the 2.25-mile widening from 200 South in Pleasant Grove to 500 East in American Fork will add three through lanes each way, a median, buffered bike lanes and rebuilt intersections at 500 East, 700 East and North County Boulevard; a new signal at 860 East was split off as a separate project to start within a month and finish by spring. High right-of-way costs used up the original funding; acquisition should finish within months and construction is planned for spring 2024, possibly 2023. Council members asked about the Rail Line Trail, 700 East grade changes and the speed limit, which will stay the same.
- Length: 2.25 miles
- New signal at 860 East to be installed separately, winter 2020-21
- Construction: spring 2024 (possibly 2023)