Fire Station 52
New Fire Station 52: at the Oct. 24, 2023 meeting the city administrator announced a ribbon cutting and open house, thanking residents who voted for the bond; SIRQ Construction was the contractor and Blalock & Partners the architect.
Approved
- Type
- Public project
- Location
- Northeast American Fork
- Applicant
- American Fork City
- City Council: Fire Station 52 ribbon cutting
- City Council: Administrator's report: Fitness Center bubble, dog park, Fire Station 52
- City Council work session: FY2023 capital projects and budget status
- City Council: State of the City address
- City Council: Amended CMGC contract with SIRQ Construction for Fire Station 52
In brief
Fire Station 52 appears on 16 recorded agendas, from the City Council meeting of January 14, 2020 to the City Council meeting of October 24, 2023.
On record, it was approved 3 times and approved with conditions once.
The most recent decision was approved (4-0-1) at the City Council meeting of August 23, 2022.
Follow the money and project delivery
Fire Station 52
- Council action
Approved according to the dated project source. Record → · Oct. 24, 2023
- Money in the record
contract: $9.11 million — Guaranteed maximum price for construction of Fire Station 52 with shooting range; budget: $11.6 million — Total Fire Station 52 project cost including land Record → · Aug. 23, 2022
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
October 24, 2023 · City Council
Fire Station 52 ribbon cutting
No action
Bunker announced the ribbon cutting for the bond-funded Fire Station 52, built by contractor SIRQ Construction with architect Blalock & Partners, with an open house for Cedar Hills residents.
September 26, 2023 · City Council
Administrator's report: Fitness Center bubble, dog park, Fire Station 52
No action
Staff erected the Fitness Center pool bubble in-house, saving money. Doug Smith Subaru Dog Park dedication set for Oct. 14; Fire Station 52 ribbon cutting Oct. 26.
February 16, 2023 · City Council work session
FY2023 capital projects and budget status
Discussed
Station 52 to finish this summer; up to $12 million in road improvements rolled over; 200 South funded; 700 North connection geotech 95% designed; signal materials bought for 620 South 600 East; water line Segment 3 done and Segment 4 out to bid; CDBG Phase 10 funded. Building permit revenue down. Outstanding bonds: PI (2035), Art Dye and cemetery (2028), Station 52 (2038), 36-inch waterline (2041), TOD 200 South (2047); bond rating AA-. PARC awards about $1.7 million in May, including $390,000 in reserves.
January 24, 2023 · City Council
State of the City address
No action
Frost said the city would improve about 5 million square feet of roadway in 2023; 200 South reconstruction would start spring 2023 and finish late 2024; the 700 North connection (100 East to 200 East, MAG-funded, signal and roundabout) would take 18-24 months; the $12 million PI meter project was paid almost entirely with grants, with 3,400 meters installed; the city partnered with Strata Networks on city-owned fiber; Fire Station 52 (16,500 sq. ft.) was due by July; Moody's upgraded the city's rating; PARC funded 24 projects totaling $1.2 million, including six lighted pickleball courts at Hindley Park.
August 23, 2022 · City Council
Amended CMGC contract with SIRQ Construction for Fire Station 52
Approved · 4-0-1
SIRQ Construction was hired as construction manager/general contractor in October 2020 before a site or plans existed; with land secured and subcontractor bids in, the council set a guaranteed maximum price of $9,112,335, with value engineering that could save $150,000-$300,000. Total project cost is $11,590,311, higher than expected due to inflation and land cost, funded by 2019 bond proceeds and police and fire impact fees (about $2.5 million each). The station includes a shooting range on the west side; options to leave it unfinished ($692,784 savings) or omit it ($1,038,120) were rejected. Bunker said moving out of Cedar Hills' station will add about $300,000 a year in costs to that contract.
- Contractor: SIRQ Construction (CMGC selected October 2020)
- GMP: $9,112,335
- Total project: $11,590,311
- Shooting range options: unfinished -$692,784; omitted -$1,038,120
- Councilmember Ryan Hunter abstained because he works for SIRQ Construction
- SIRQ also sponsored the city's firefighter challenge event that Hunter helped organize (Dec. 13, 2022 minutes)
May 10, 2022 · City Council
Fire Station 52 final plat and site plan (Ordinance 2022-05-21)
Approved with conditions · 4-0
Approved the final plat consolidating parcels and the site plan for Station 52, which will serve north American Fork and Cedar Hills and include a police training facility. Access from 1750 North confirmed; an evidence building could come in a future phase.
April 19, 2022 · City Council work session
FY2023 general fund and fleet fund
Discussed
Finance Director Anna Montoya presented the FY2023 general fund. The fund balance grew from under $3 million in 2019 to $11 million in 2021. Personnel up 9.1% and operations 20.3%, driven by inflation, a tight labor market and growth. Proposed additions: a full-time assistant city administrator, a full-time forester and tree division, a part-time Spanish outreach liaison at the library, three police officers (six requested), two part-time GRAMA records specialists, a firefighter/paramedic, and a streets technician. Shelton, Taylor and Carroll questioned a full-time forester. The working tax scenario raised the rate from .001448 to .001948, about $1.7 million or $169 per household per year.
- Public safety is 49% of the general fund; personnel 65%.
- Police capital: five replacement, three additional and two unmarked vehicles.
- Fire Station 52 staffing goal: six more to staff another ambulance.
- Shelton asked that the court lease increase being negotiated with the state go to police and asked for a copy of the agreement.
- Permit revenue: about $2 million in 2021 versus $1.386 million budgeted for 2022.
March 15, 2022 · City Council work session
FY2023 capital projects and RDA funds
Discussed
Requested public works capital totaled $5,712,477, including $2.88 million for infrastructure management, $1.776 million for the 700 North connection road and $850,000 for 300 West improvements. Other requests: Fire Station 52 and police range, Fire Station 53 land, a police/courts feasibility study, and building repairs. The Egg Farm EDA has about $1.4 million for 1100 South and possibly 1500 South widening.
February 10, 2022 · City Council work session
Community survey, goals and FY2022 status
Discussed
Camden Bird reported 1,476 survey responses: 90% rated quality of life good or excellent; top issues were poor roads, too much growth and internet access. 47% would support a fee or tax increase for roads (45% no). Updates: the 30-acre south-side park purchase was locked in; Fire Station 52 land bought and in design; Fire Station 53 land purchased; 36-inch water line segment 3 awarded; PI meter supplies ordered with a matching grant. Revenues were up 22.7% and sales tax 12.1%. $927,000 in PARC Tax is available for May awards.
January 25, 2022 · City Council
State of the City address
No action
Mayor Frost reported 1,180 building permits in 2021, about 30,000 police and 4,772 fire calls, nearly $10 million in grants, $3.4 million in ARPA money aimed at secondary water metering, a fully funded general fund reserve, almost a billion gallons of water saved, about $4.3 million spent on roads, and the purchase of 30 acres south of I-15 with park impact fees for a park and the third fire station. He cited a $43 million regional project to widen State Street into Pleasant Grove.
October 13, 2020 · City Council
Fire Station 52 construction manager/general contractor contract
Approved · 5-0
The council approved a CMGC contract with SIRQ Inc. for Fire Station 52, with a deadline corrected to April 15, 2021. Schematic design is largely done. Per the packet, eight firms answered a request for qualifications; preconstruction services are $4,475, the fee is 3% of the cost of work, and the guaranteed maximum price will be set later against a construction budget of about $5.2 million from the voter-approved bond.
- Selection: RFQ, 8 statements of qualifications, panel chose SIRQ Inc.
- Construction budget: about $5.2 million (voter-approved bond)
June 2, 2020 · City Council work session
FY2021 city budget review
Discussed
Total budget $102 million; General Fund just over $23 million (revenue $22.7 million, with a $2 million transfer back from capital projects to cover COVID-19 shortfalls); all-fund revenue $85.45 million; capital projects over $55 million. Highlights: culinary water line about $28-29.5 million (state loan), fire station $8.4 million (bonds), road plan $2.093 million (Class B/C, $500,000 property tax and transportation sales tax), 700 North connection $1.923 million (MAG grant), 200 South bike/pedestrian path $4.1 million (MAG grant), pressurized irrigation meters $3 million with a $1.5 million matching grant, and a $2 million placeholder for a PI pump and land to recapture TSSD water pending a study (water rights legal work $30,000-$50,000; study a couple hundred thousand dollars). New positions: three firefighters, a battalion chief, a police officer, a sergeant, two part-time records clerks and a civil engineer. Shelton objected to cutting water line repairs from $300,000 to $100,000 (staff had recommended $500,000) with about $13 million in the water fund, and said the city was not following its published road plan; Carroll wanted every possible dollar on roads.
April 21, 2020 · City Council work session
FY2021 water, sewer, perpetual care, capital, broadband and IT budgets
Discussed
Culinary water: an $18.34 million water line, 85% funded by a state loan applied for with the rest from water impact fees; 20% of debt service ($161,000) from the water fund; a city engineer added; 3% raises; no CDBG grant expected. Secondary water: a $1.5 million Bureau of Reclamation grant for PI meters with a $1.6 million city match (phase one $3.1 million, covering 25-30% of meters); culinary water subsidizes secondary water by $870,000, which Shelton said should be treated as a loan. Reserves after targets: culinary $13.3 million, secondary $7.8 million. Capital: $8.4 million public safety (bonds closing May 6 at about 1.8%; $6.4 million for a fire station and shooting range plus $2 million for land), $4.8 million parks (200 South bike/pedestrian path, MAG-funded), $4.22 million public works including $1.96 million pavement management (of $2.2 million requested) and $1.098 million for the 700 North connection; the Art Dye roundabout budget was cut $150,000 because estimates came in under $500,000. Shelton wanted the $500,000 he recalled from the 2007 property tax increase for roads; staff calculated $252,000.
April 14, 2020 · City Council
Fire Station 52 architectural design contract to Blalock and Partners
Approved · 5-0
The fire chief, police chief and public works director scored seven proposals with and without cost after a mandatory pre-proposal meeting advertised on SciQuest and the city website. Shelton asked why JRCA, which had contacted the city after the bond, did not submit; staff said JRCA attended the pre-proposal meeting. Kevin Blalock said the firm designed Spanish Fork's new fire station and several Salt Lake City stations.
February 27, 2020 · City Council work session
Community survey and 2020 strategic goals update
Discussed
Camden Bird said road repair is again residents' top issue, followed by managing growth. Fire Station 52: land acquisition under way, architect RFQ drew about a dozen firms, bond expected in April. Downtown revitalization consultant delivered a high-level report.
January 14, 2020 · City Council
State of the City address
No action
Frost cited a record 795 building permits worth $180 million in 2019, 3,910 fire calls (the busiest station in Utah County), plans to seek design qualifications for a second fire station, Canal Boulevard and a 700 North link between 100 East and 200 East with MAG funding, a MAG-funded transit circulator study, $4 million in PARC-funded projects, Amazon and Built Bar arriving, a Woodbury office tower in the Opportunity Zone, and a study of using city-owned fiber.