700 North / 200 East improvements
Road and utility improvements around 700 North and 200 East. In 2024 the city bought land from Sonya Laney (May 28) and a 6-square-foot slope and utility easement from Anita Gibson (June 25); the 700 North connector design was complete with bids pending.
- Where it stands
- Approved
- Type
- Road project
- Location
- 700 North and 200 East
- Size
- 1.678 acres
- Applicant
- American Fork City
Every hearing and vote
February 22, 2024 · City Council work session
FY2024 strategic goals and capital project status
Discussed
Fiber high-level design done, mid-level 80%, construction hoped for summer. Facilities master plan going to bid (including the 30-acre property). Water reuse permit applied for. Projects: 200 South Phase 1 soon; street overlay of 800,000 sq ft; reconstruction of 300 North, 200 South, 200 East; 700 North connector design complete with bids forthcoming; signal at 620 South 600 East; Auto Mall Drive bids April 2024; 1100 South widening design complete; 36-inch waterline Segment 3 complete, 18-inch Segment 4 in spring; PI meters Phase 2 80% and Phase 3 under construction; 1120 North bridge precast culvert in spring; 900 East curb and gutter in design; Boat Harbor restroom and parking in design; Hindley Park pickleball.
April 23, 2024 · City Council work session
FY2025 general fund, capital projects and fleet budget
Discussed
Revenue: taxes up $1,111,222 (5% new growth, no rate increase), charges for services up $1,313,007 (renegotiated Cedar Hills public safety contract, court rent), interest and misc. up $718,059 including $500,000 developer streetlight contributions. 5.5 new FTEs. Fire budget $7.9 million (+$832,000). Planning: $250,000 downtown revitalization plan; council members said they wanted action, not another study. Public works capital $12.6 million: $3.5 million road improvement plan, $1.4 million Auto Mall connection side path (impact fees), 200 South roundabouts at 300 West and 100 East, 700 North, 300 North/600 East intersection, 700 South extension. Community services $8.4 million: boat harbor, 200 South trail, $250,000 park designs, Rotary lights $450,000 with PARC match, $240,000 Fox Hollow contribution. Other: $1.5 million downtown property reserve, $400,000 electronic billboard, $300,000 police evidence building. Fire Station 53 not funded yet; the city expected to close on its land in the fall.
- Public works capital: $12.6 million
- Road improvement plan: $3.5 million
- Auto Mall connection side path: $1.4 million
- Community services capital: $8.4 million
- Downtown revitalization reserve: $1.5 million
- Electronic billboard: $400,000
- Police evidence building: $300,000
May 28, 2024 · City Council
Real estate purchase from Sonya Laney, about 700 North 200 East
Approved · 5-0
Purchase agreement for property needed for 700 North / 200 East improvements; the amount is not in the minutes and the packet exceeds 50 MB.
June 25, 2024 · City Council
Purchase of 6 square feet from Anita Gibson, about 690 North 200 East
Approved · 4-0
Real estate purchase agreement for a tiny public utility and slope easement ahead of improvements at 700 North and 200 East.
August 25, 2026 · City Council
Reimbursement agreement with Deborah and Maurice Navarro, 247 E. 700 North
Pending
Reimbursement of up to $38,085 for upsizing 700 North (a legacy arterial with 44 feet of asphalt) and a 10-foot side path beyond the minimum improvements required for the Navarro home on a 1.678-acre parcel: up to $29,440 from road impact fees and $8,645 from park impact fees.
- Total: $38,085