About 30 acres the city budgeted to buy in 2022 ($3 million plus park impact fees, a $6.2 million budget line), planned for 28 acres of parks and a 2-acre site for a third fire station.

Where it stands
Approved
Type
Public project
Location
South American Fork near Lakeshore

Every hearing and vote

  1. January 25, 2022 · City Council

    State of the City address

    No action

    Mayor Frost reported 1,180 building permits in 2021, about 30,000 police and 4,772 fire calls, nearly $10 million in grants, $3.4 million in ARPA money aimed at secondary water metering, a fully funded general fund reserve, almost a billion gallons of water saved, about $4.3 million spent on roads, and the purchase of 30 acres south of I-15 with park impact fees for a park and the third fire station. He cited a $43 million regional project to widen State Street into Pleasant Grove.

  2. February 10, 2022 · City Council work session

    Community survey, goals and FY2022 status

    Discussed

    Camden Bird reported 1,476 survey responses: 90% rated quality of life good or excellent; top issues were poor roads, too much growth and internet access. 47% would support a fee or tax increase for roads (45% no). Updates: the 30-acre south-side park purchase was locked in; Fire Station 52 land bought and in design; Fire Station 53 land purchased; 36-inch water line segment 3 awarded; PI meter supplies ordered with a matching grant. Revenues were up 22.7% and sales tax 12.1%. $927,000 in PARC Tax is available for May awards.

  3. February 10, 2022 · City Council work session

    FY2023 strategic goals

    Discussed

    Possible goals: fiber, property acquisition for parks and public works, a master plan for the 30-acre south-side purchase, an investment strategy, a downtown master plan with police/courts and offices, employee morale, communication, the code rewrite, 200 South funding and water recycling with TSSD.

  4. May 17, 2022 · City Council work session

    FY2023 strategic goals

    Discussed

    Camden Bird listed goals: citywide fiber; 200 South design, bonding, bid and construction starting September 2022; a 30-year facilities master plan including a 30-acre property (28 acres for parks, 2 for a third fire station near Lakeshore); pressurized irrigation metering and rates by spring 2023; a water recycling concept modeled by Horrocks; and a full city code rewrite with the development code outsourced. The mayor said residents saved 245 million gallons from April 15 to May 15 versus the 10-year average.

  5. June 14, 2022 · City Council

    Amended fiscal 2022 budget (Resolution 2022-06-20R)

    Approved · 5-0

    Amended the FY2022 budget. Montoya said $3 million had been budgeted to buy 30 acres of open space on the south side of town, with more added from PARC impact fees, under a line labeled 'Art Dye expansion' totaling $6.2 million.

    • 30-acre south-side open space: $3M budgeted plus PARC impact fees ($6.2M line)

    Moved by Councilmember Barnes, seconded by Councilmember Taylor. Vote: 5-0