Lehi development tracker

Thanksgiving Point Housing Transit Reinvestment Zone

The state approved the Thanksgiving Point Housing and Transit Reinvestment Zone in November 2023, allowing property tax growth in the zone to help pay for mixed-use development near transit. A Lehi City Council agenda for Oct. 21, 2026 listed Resolution 2026-63, an interlocal agreement letting the Redevelopment Agency receive 80 percent of that increment, up to $122,144,769, over up to 45 years. The result of that item is not yet reported.

In reviewStatus as of Oct 21, 2026

Type
Development agreement
Location
Thanksgiving Point area
Applicant
Thanksgiving Station Development Partners, LLC
  1. Oct 21, 2026City Council: Interlocal agreement with the Redevelopment Agency for the Thanksgiving Point Housing and Tra…
  2. Oct 13, 2026City Council: Thanksgiving Point Housing Transit Reinvestment Zone interlocal agreement
  3. Jul 14, 2026City Council: Thanksgiving Point Housing Transit Reinvestment Zone interlocal agreement (Resolution 2026-43)
  4. Jun 9, 2026City Council: Thanksgiving Point HTRZ interlocal agreement (Resolution 2026-43)
  5. May 12, 2026City Council: Thanksgiving Point HTRZ interlocal agreement (Resolution 2026-29)

In brief

Thanksgiving Point Housing Transit Reinvestment Zone appears on 18 recorded agendas, from the City Council meeting of April 12, 2022 to the City Council meeting of October 21, 2026.

On record, it was approved once and continued once.

The most recent decision was continued at the City Council meeting of May 12, 2026.

The most recent agenda collected for it, the City Council meeting of October 21, 2026, listed it with no result recorded.

Follow the money and project delivery

Thanksgiving Point Housing Transit Reinvestment Zone

In review

  1. Council action

    In review according to the dated project source. Record → · Oct. 21, 2026

  2. Money in the record

    incentive-cap: $122.1 million — Proposed ceiling on the property tax increment the agency could receive from the zone (80% of increment, 25 years per parcel, 45-year cap); a limit in a proposed agreement, not money paid Record → · Oct. 21, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. October 21, 2026 · City Council

    Interlocal agreement with the Redevelopment Agency for the Thanksgiving Point Housing and Transit Reinvestment Zone

    Pending

    Resolution 2026-63 would approve an agreement between Lehi City and the Lehi City Redevelopment Agency (RDA) for the Thanksgiving Point Housing and Transit Reinvestment Zone, which the state's Housing and Transit Reinvestment Zone Committee approved Nov. 13, 2023. The city would consent to the agency receiving 80 percent of the property tax increment the zone generates, up to $122,144,769. Collection for each parcel would run 25 full calendar years from a trigger year, could not begin until a temporary certificate of occupancy is issued for a building on that parcel, and no parcel could be triggered more than once. The total collection period is capped at 45 years. The agency could use the money to reimburse developer costs allowed by state law and to cover its own administrative and legal expenses, and could sign a participation agreement with Thanksgiving Station Development Partners, LLC. The resolution says the agreement matches the state approval, obligates only increment actually collected and distributed by the county, and does not pledge the city's General Fund. It takes effect 30 days after the required public notice is first published. Mayor Paul Binns signs for the city and as chair of the RDA.

    • Resolution: 2026-63
    • City share to agency: 80% of tax increment
    • Maximum: $122,144,769
    • Per-parcel period: 25 years; total period: 45 years
    • Expected developer: Thanksgiving Station Development Partners, LLC
    • State approval of zone: Nov. 13, 2023
  2. October 13, 2026 · City Council

    Thanksgiving Point Housing Transit Reinvestment Zone interlocal agreement

    Pending

    Interlocal agreement between the RDA and city on the Thanksgiving Point Housing TRZ.

  3. July 14, 2026 · City Council

    Thanksgiving Point Housing Transit Reinvestment Zone interlocal agreement (Resolution 2026-43)

    Pending

    After a Redevelopment Agency meeting, the council considered an interlocal agreement between the RDA and the city on the Thanksgiving Point Housing Transit Reinvestment Zone. No staff report was in the packet; a similar agreement returned on the Oct. 13 agenda.

  4. June 9, 2026 · City Council

    Thanksgiving Point HTRZ interlocal agreement (Resolution 2026-43)

    Pending

    Resolution 2026-43 would approve an interlocal agreement between the Redevelopment Agency and the city on the Thanksgiving Point zone.

  5. May 12, 2026 · City Council

    Thanksgiving Point HTRZ interlocal agreement (Resolution 2026-29)

    Continued

    Postponed to May 26 on the agenda.

  6. April 14, 2026 · City Council

    Thanksgiving Point HTRZ interlocal agreement (Resolution 2026-29)

    Pending

    Resolution 2026-29 would approve an interlocal agreement between the Lehi Redevelopment Agency and the city on the Thanksgiving Point Housing Transit Reinvestment Zone.

  7. March 24, 2026 · City Council

    Thanksgiving Point participation agreements (pre-council)

    Discussed

    Pre-council discussion covered an HTRZ participation agreement between the Lehi Redevelopment Agency and Thanksgiving Station Development Partners, LLC, a second with STACK Soccer Field, LLC, and an interlocal agreement with the city.

  8. February 9, 2026 · City Council work session

    Thanksgiving Point development agreement and participation agreement

    Pending

    Presentation and discussion listed on the agenda.

  9. December 16, 2025 · City Council

    New U.S. Treasury regulations on bond hearings

    Discussed

    Finance Director Dean Lundell said new Treasury regulations require a public comment period to meet IRS requirements for the Thanksgiving Point bond. It need not be a council meeting, only a call-in line; an electronic hearing was set for Dec. 19.

  10. December 2, 2025 · City Council

    Public hearing on Series 2025B bonds

    No action

    The council held a hearing on issuing the Series 2025B bonds and their potential economic effect on the private sector. Laura Stevens and Cody Black each spoke against issuing the bonds. No vote was taken on the issuance at this meeting.

  11. July 22, 2025 · City Council

    Thanksgiving Point economic and fiscal impact study

    Discussed

    Thanksgiving Point CEO McKay Christensen and consultant Jason Burningham presented a study projecting $8.3 billion in economic impact over 25 years and $403.2 million in fiscal impact, of which Lehi would receive about $53.8 million, or about $2.2 million a year, mostly sales tax. They said Lehi residents made over 300,000 visits last year and PARC days cost $5 instead of $24. Mayor Johnson said an in-house estimate had been about $600,000 a year. The study is by the organization that receives PARC tax funds.

  12. October 25, 2022 · City Council

    Thanksgiving Point Housing and Transit Reinvestment Zone designation (Resolution 2022-93)

    Approved · 5-0

    Economic Development Director Marlin Eldred said the resolution only starts the process of analysis. The council designated the proposed zone and authorized staff and counsel to prepare a proposal.

    Moved by Council Member Mike Southwick, seconded by Council Member Katie Koivisto. Vote: 5-0

  13. October 11, 2022 · City Council

    Thanksgiving Point area plan amendment update (pre-council)

    Discussed

    John Bankhead said trigger points for the area plan have been identified and will be in the traffic report. Members discussed the land use table, with suggestions to add adult day care and assisted living. He said power limits will need to be addressed and that the power-based density cap (estimated at 800 units) will likely be lower than the traffic-based cap; the office cap will be based on acreage. He said impact fees should cover most improvements, the State would fund larger ones such as a Clubhouse Drive extension, and the city is also exploring a Housing and Transit Reinvestment Zone.

  14. July 26, 2022 · City Council

    Thanksgiving Point transit-oriented development update

    Discussed

    Jonathan Bankhead said the project is working through a development code amendment and plans to submit smaller sections of the area plan so approvals can proceed on a smaller scale.

  15. July 12, 2022 · City Council

    UTA station area plan for the Thanksgiving Point FrontRunner station

    Discussed

    Planning Director Kim Struthers said UTA is studying its 11-acre parcel at the station, as the council asked when it approved the transit-oriented development concept plan, and is working closely with the developer. The study is in its community engagement phase, with an open house planned and a goal of finishing by mid-September. Mike West explained the housing and transit reinvestment zone requirements, said demand is high for apartments with some retail, and showed possible design and land use options aimed at creating a sense of place.

  16. June 14, 2022 · City Council

    Thanksgiving Point HTRZ funding discussion

    No action

    The item was postponed again to a future meeting.

  17. May 24, 2022 · City Council

    Thanksgiving Point HTRZ funding discussion

    No action

    The item was postponed to a future meeting.

  18. April 12, 2022 · City Council

    Thanksgiving Point housing and transit reinvestment zone funding briefing

    Discussed

    Marlin Eldred presented on the Thanksgiving Point preliminary plan and the process and expenses involved. A housing and transit reinvestment zone (HTRZ) is a funding tool created by the Legislature for development near FrontRunner or TRAX stations. The presentation focused on planning ahead for infrastructure maintenance costs.