Lehi council approves UDOT utility and trail agreements for 2100 North and a Dry Creek flood plan

July 22, 2025, 5:13 p.m. · Council Chamber, Lehi City Hall, 153 N. 100 East

The Lehi City Council approved four agreements with UDOT tied to the 2100 North freeway project, a Rino Excavating contract of about $500,000 for the Lambert Basin storm drain, the Upper Inverness grading permit and an NRCS watershed agreement for Dry Creek flood work. In pre-council the council discussed pressurized irrigation rates and a revised SHAR housing ordinance. All votes were unanimous.

From the approved minutes. Updated October 14, 2026.

Decisions at a glance

Agenda, item by item

  1. Item 2.1 · Taxes and fees

    Pressurized irrigation water rates

    Discussed

    Consultant Fred Philpot reviewed Lehi's rate (charged per connection by lot size), a recent Alpine study that added base rates per acre and tiers by customer class, and Saratoga Springs, Spanish Fork and Springville systems. About half of roughly 14,000 unmetered connections have been metered since the state mandate. Mayor Johnson noted Saratoga Springs' system draws few complaints. Council Member Condie favored a simple tiered system, Council Member Hancock said conservation should not be punitive, and the council favored a slow rollout and giving residents access to usage data.

  2. Item 2.2 · Presentation

    Thanksgiving Point economic and fiscal impact study

    Discussed

    Thanksgiving Point CEO McKay Christensen and consultant Jason Burningham presented a study projecting $8.3 billion in economic impact over 25 years and $403.2 million in fiscal impact, of which Lehi would receive about $53.8 million, or about $2.2 million a year, mostly sales tax. They said Lehi residents made over 300,000 visits last year and PARC days cost $5 instead of $24. Mayor Johnson said an in-house estimate had been about $600,000 a year. The study is by the organization that receives PARC tax funds.

    • Budget$2.20 million Estimated annual fiscal benefit to Lehi City from Thanksgiving Point, per the organization's study

    Follow Thanksgiving Point Housing Transit Reinvestment Zone in the development tracker →

  3. Item 2.3 · City code

    Draft SHAR overlay ordinance

    Discussed

    Planner Brittney Harris presented a revised draft with new definitions, attainability standards and setbacks matching planned communities. It is no longer a citywide overlay: council would decide through development agreements. Attainable lots would be deed restricted to owner occupancy in perpetuity, with similar materials as standard homes and a proposed price point of $400,000. Council Member Stallings said the draft devalues landowners' property and saw affordable housing and free-market land pricing as in conflict; Council Member Newall worried that earmarking areas creates entitlements; Mayor Johnson did not want council controlling the market; Council Member Albrecht asked why a similar earlier overlay was denied. City Engineer Brad Kenison said engineering prefers this version.

    Follow SHAR affordable housing overlay in the development tracker →

  4. Item 6 · Development

    Upper Inverness grading permit, 693.4 acres

    Approved with conditions · 5-0

    Landon Larsen of D.R. Horton said the aim is to keep fill on site rather than truck it out and back, and the site is meant to balance. The permit was approved with Development Review Committee and Planning Commission comments; an extension would need to be requested if work runs past the allowed time.

    • Acres: 693.4
    • Applicant: D.R. Horton

    Moved by Council Member Chris Condie, seconded by Council Member Heather Newall. Vote: 5-0; unanimous

    Follow Upper Inverness grading permit in the development tracker →

  5. Item 7 · Roads and utilities

    Lambert Basin storm drain construction agreement with Rino Excavating (Resolution 2025-49)

    Approved · 5-0

    City Engineer Lorin Powell said 13 bidders responded and the city chose the low bid from Rino Excavating, with which it has past experience. The bid was about half a million dollars. The project connects retention basins with a 48-inch pipe under the freeway and railroad tracks; work was expected to start in three to four weeks.

    • Contract$500,000 to Rino Excavating Lambert Basin storm drain (approximate bid). Low bid of 13

    Moved by Council Member Paul Hancock, seconded by Council Member Paige Albrecht. Vote: 5-0; unanimous

    Follow Lambert Basin storm drain in the development tracker →

  6. Item 8 · Roads and utilities

    UDOT master agreement for utility work on the 2100 North project (Resolution 2025-50)

    Approved · 5-0 · 2100 North

    Kenison said the agreement sets design criteria for city utilities within UDOT's project. UDOT's Matt Parker said the current work ends east of Redwood Road in early spring, when the 2100 North project begins; proposals are due just after Labor Day. He said a Pioneer Crossing contractor starts in about a month with completion by the end of next summer. A pedestrian bridge over SR-92 is a standalone project with an estimated cost of $7 million, for which alternative funding is sought.

    Moved by Council Member Chris Condie, seconded by Council Member Heather Newall. Vote: 5-0; unanimous

    Follow 2100 North freeway (Mountain View Corridor to I-15) in the development tracker →

    Follow Pioneer Crossing Flex Lanes (Redwood Road to I-15) in the development tracker →

    Follow SR-92 / Center Street pedestrian bridge in the development tracker →

  7. Item 9 · Roads and utilities

    UDOT supplemental agreement for utility stubs across the freeway (Resolution 2025-51)

    Approved · 5-0 · 2100 North

    Kenison and Parker said the agreement lets the city stub master-plan water, sewer, irrigation and storm drain lines across the freeway before surrounding structures are built, by adding bid items to UDOT's original contract rather than change orders. The work will be competitively bid and council can review it.

    Moved by Council Member Heather Newall, seconded by Council Member Chris Condie. Vote: 5-0; unanimous

    Follow 2100 North freeway (Mountain View Corridor to I-15) in the development tracker →

  8. Item 10 · Parks

    UDOT agreement for trail connection through Holbrook Park 2 (Resolution 2025-53)

    Approved · 5-0 · Holbrook Park 2, Jordan River bridge to Waterbury Drive

    The asphalt trail would connect the Jordan River pedestrian bridge to Waterbury Drive, replacing trails now on UDOT bridges that are being removed. The project is estimated at $170,000.

    • Contract$170,000 to UDOT Estimated cost of asphalt trail connection. Agreement with UDOT

    Moved by Council Member Paul Hancock, seconded by Council Member Paige Albrecht. Vote: 5-0; unanimous

    Follow 2100 North freeway (Mountain View Corridor to I-15) in the development tracker →

  9. Item 11 · Roads and utilities

    UDOT agreement for access road from 2100 North and Thanksgiving Way to park-and-ride (Resolution 2025-54)

    Approved · 5-0 · 2100 North and Thanksgiving Way

    Under UDOT's current design the Hadco access would become right-in, right-out, so the city and UDOT agreed to an additional access to Thanksgiving Way if that design is selected. Costs would be shared with Hadco as a shared access. The connection would improve park-and-ride access, which the project prioritizes; the project may not happen, depending on the design chosen.

    Moved by Council Member Chris Condie, seconded by Council Member Heather Newall. Vote: 5-0; unanimous

    Follow 2100 North freeway (Mountain View Corridor to I-15) in the development tracker →

  10. Item 12 · Appointment

    Appointment to the Metropolitan Water District of Lehi board (Resolution 2025-52)

    Approved · 5-0

    Lorin Powell is retiring from the board and will consult for it; Brad Kenison was appointed as his replacement.

    Moved by Council Member Paul Hancock, seconded by Council Member Heather Newall. Vote: 5-0; unanimous

  11. Item 13 · Roads and utilities

    American Fork Dry Creek Watershed Agreement with the NRCS (Resolution 2025-55)

    Approved · 5-0 · Dry Creek near Lehi Elementary

    Kenison and consultant Parker Versimac of Jones and DeMille said the agreement, required by the Natural Resources Conservation Service for funding, amends a 1959 watershed plan to address flooding, studied jointly with American Fork and Saratoga Springs as co-sponsor. Proposed work includes replacing two corrugated metal culverts near Lehi Elementary with box culverts and trash racks. The plan works with a $25 million budget; NRCS pays for design and the city owes nothing until construction, when it may have to buy right of way and fund bridge and culvert improvements after federal funding for them was rescinded.

    Moved by Council Member Chris Condie, seconded by Council Member Heather Newall. Vote: 5-0; unanimous

    Follow American Fork Dry Creek watershed plan in the development tracker →

  12. Item 14 · Other

    Closed meeting on pending or imminent litigation

    Approved · 5-0

    The council voted to go into a closed meeting.

    Moved by Council Member Paige Albrecht, seconded by Council Member Paul Hancock. Vote: 5-0; unanimous

What residents said

SHAR housing ordinanceWater supply and aquifer levelsGraywater useCanal weeds

Several speakers, including James Harrison, Tyson Hodges, Rachel Freeman and LaRell Stephens, raised concerns about the SHAR ordinance, including bonus density, lack of cost control after the first buyer, and neighborhood identity. Hodges also asked the city to address canal weeds by a development. Bradley Anderson raised water sustainability after a natural pond on his property dried up; Lorin Powell said the Murdock Canal lost about 20% of its water in Highland and the city is pursuing aquifer recharge. LaRell Stephens asked about graywater, and Stephen Su'a-Filo asked for more water rights education.