2300 West widening
Lehi is widening 2300 West from three to five lanes. The FY2025-26 budget carries two MAG-funded line items: Main Street to 2100 North ($7 million budgeted, $7 million total) and Main Street to Pioneer Crossing ($1 million budgeted this year of a $12 million total). UDOT's Pioneer Crossing project is separately relocating utilities and adding turn lanes at 2300 West through late 2026. The city has not posted a firm completion date on its website.
Under construction
- Type
- Road project
- Applicant
- Lehi City
- Run by
- Lehi
- Cost
- $19.0 million
- Location
- 2300 West, Pioneer Crossing to Main Street
- Paid for by
- Mountainland Association of Governments (MAG)
- City Council: 2300 West right-of-way purchase from Edward L. Crossman (Resolution 2026-52)
- City Council work session: 2300 West fence
- City Council: Second amended interlocal agreement with Utah County for 2300 West widening (Resolution 2025-71)
- City Council: 2300 West widening interlocal agreement with MAG (Resolution 2025-41)
- City Council: 2300 West design options, 300 North to 900 North
In brief
2300 West widening appears on 12 recorded agendas, from the City Council work session meeting of February 1, 2022 to the City Council meeting of September 22, 2026.
On record, it was approved 8 times.
The most recent decision was approved (4-0) at the City Council meeting of September 23, 2025.
The most recent agenda collected for it, the City Council meeting of September 22, 2026, listed it with no result recorded.
Follow the money and project delivery
2300 West widening
- Council action
Approved: Second amended interlocal agreement with Utah County for 2300 West widening (Resolution 2025-71) · Approved minutes Record → · Sept. 23, 2025
- Money in the record
land: $256,000 — Right-of-way (parcel 21) and utility easement for 2300 West widening Record → · Sept. 22, 2026
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
September 22, 2026 · City Council
2300 West right-of-way purchase from Edward L. Crossman (Resolution 2026-52)
Pending
Buys parcel 21 and a utility easement at 656 S. 2300 West for the 2300 West widening from two lanes to five between Pioneer Crossing and Main Street. The $256,000 total covers 7,769 square feet of land at $18 per square foot ($139,842), a 4,061-square-foot utility easement at 50% ($36,549), improvements ($29,639), cost to cure ($10,684), damages for loss of access ($39,204) and $82 rounding. A water well on the property is handled separately.
- Seller: Edward L. Crossman
- Total: $256,000
September 21, 2026 · City Council work session
2300 West fence
Discussed
Discussion of fencing along the 2300 West widening.
September 23, 2025 · City Council
Second amended interlocal agreement with Utah County for 2300 West widening (Resolution 2025-71)
Approved · 4-0
City Engineer Lorin Powell said the amendment extends the contract so striping and an overlay can be done in the spring.
June 10, 2025 · City Council
2300 West widening interlocal agreement with MAG (Resolution 2025-41)
Approved · 5-0
Kenison said the request is about $12 million in Mountainland Association of Governments funds to widen 2300 West between Main Street and Pioneer Crossing and add two traffic signals. Design is this year, with construction projected for 2027-28, and MAG will pull forward $1 million to begin design. An eight-foot trail is planned on the north side. The current widening north of Main Street finishes in fall 2025 and cost about $13 million.
October 22, 2024 · City Council
2300 West design options, 300 North to 900 North
Discussed
City Engineer Brad Kenison presented options after property owners raised drainage, slope and fence concerns on a stretch where right-of-way was bought in 2005. Alternative 2A, about $165,000, steepens side slopes and adds a V-ditch or gravel French drain while keeping the existing fence. Alternative 2B added an 8-foot slatted fence at about $95 per foot, and Alternative 3, $790,000, would extend the slope to property lines, possibly with retaining walls. The council agreed to proceed with 2A, and the mayor directed staff to tell owners they may upgrade fencing at their own expense.
September 24, 2024 · City Council
2300 West road design update
Discussed
Assistant City Engineer Brad Kenison said the contractor was working north of 1500 North, with work including the 2100 North acceleration lane and traffic signal due between Oct. 15 and 31, resuming in spring, and the full road from 2150 North to Main Street expected to be striped with five lanes by fall 2025. Responding to a resident's request for a west-side sidewalk, he said the right of way has been in the Transportation Master Plan since 1980 and the property was acquired in 2022, that sidewalks are planned from 300 North to 900 North on the east side, and that a Hawk signal at the waste ditch trail crossing and another at North Point Elementary and 2150 North were chosen over an undercrossing or overcrossing. Stormwater will go to the storm drain system; posted speed stays 35 mph. Council Member Condie asked about trails, drainage, weed control (the city will maintain) and a hard-surface path, which Kenison said could take up to 18 months to secure right of way. Council Member Stallings asked about snow removal. No vote was taken.
May 14, 2024 · City Council
Widening of 2300 West: agreement with Kenny Seng Construction (Resolution 2024-24)
Approved · 4-0
The council approved the construction agreement for widening 2300 West. Marshal Gary of Strong Towns Lehi read a letter raising concerns with the proposed design. The minutes give no amount or bid information.
May 14, 2024 · City Council
Widening of 2300 West: construction services with RB&G Engineering (Resolution 2024-25)
Approved · 4-0
The council approved an agreement with RB&G Engineering for construction services for the 2300 West widening. The minutes give no amount.
September 19, 2023 · City Council
Consent agenda: purchase orders, addenda to 55 West Main Street purchase, and 2300 West interlocal amendment
Approved · 5-0
The council approved purchase orders (no vendors or amounts listed), Addenda 2 and 3 to the earlier real estate purchase contract for 55 West Main Street, and a first amendment to the interlocal agreement with Utah County for the 2300 West widening project. The minutes give no dollar amounts.
July 25, 2023 · City Council
X Lehi LLC road dedication for 2300 West widening (Resolution 2023-47)
Approved · 4-0
The council approved an agreement with X Lehi LLC to dedicate property needed to widen 2300 West. Members discussed how and where the road would be widened and answered residents' questions about future transportation plans in the area.
May 24, 2022 · City Council
RB&G Engineering construction engineering for 2300 West widening (Resolution 2022-45)
Approved · 5-0
The council approved an agreement with RB&G Engineering for construction engineering services for widening 2300 West from Main Street to 2100 North. The minutes give no fee.
April 26, 2022 · City Council
Administrative report on road funding
Discussed
Assistant City Engineer Brad Kenison said the city is using Mountainland Association of Governments funds on many projects, that the 2300 West expansion is on track to begin this year, and that the 1900 South extension also has funding support. More property owners are willing to sell for road dedication.
April 26, 2022 · City Council
Interlocal agreement with Utah County for 2300 West widening (Resolution 2022-33)
Approved · 4-0
The council approved an interlocal cooperation agreement with Utah County for the 2300 West roadway widening project. Terms and dollar amounts are not given in the minutes.
February 1, 2022 · City Council work session
Capital projects
Discussed
City Engineer Lorin Powell showed street and water storage projects. A new culinary water tank and irrigation reservoir will serve the west side, 2300 West is being designed for build-out, a signal is planned at 1100 West and Main Street, and the 700 South cycle track should be completed this year. He discussed ideas with the Peck family for Mill Pond, which could include recreation, retail and restaurants, and wants beautification there this year. Luke Seegmiller described a traffic control center for monitoring and adjusting signals, which staff want to fund in the upcoming budget.