  1. Sep 21, 2026City Council work session: 700 South bike lanes
  2. Mar 9, 2026City Council work session: Safer Systems Approach and 700 South cycle track
  3. Feb 9, 2026City Council work session: Safer systems approach and the 700 South bike lanes
  4. Jan 13, 2026City Council: Modifying the 700 South bike lanes
  5. May 6, 2025City Council work session: 700 South cycle track improvement options

In brief

700 South bike lanes appears on 8 recorded agendas, from the City Council meeting of September 22, 2020 to the City Council work session meeting of September 21, 2026.

On record, it was approved 2 times.

The most recent decision was approved (5-0) at the City Council meeting of September 22, 2020.

Follow the money and project delivery

700 South bike lanes

Approved

  1. Council action

    Approved: 700 South cycle track design contract with Avenue Consultants (Resolution #2020-66) · Approved minutes Record → · Sept. 22, 2020

  2. Money in the record

    budget: $735,000 — Option: full curb islands; budget: $445,000 — Option: partial concrete curbing; budget: $165,000 — Option: partial parking stops; purchase: $820,000 — Option: purchase a curbing machine Record → · May 6, 2025

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. September 21, 2026 · City Council work session

    700 South bike lanes

    Discussed

    Discussion of bike lanes on 700 South.

  2. March 9, 2026 · City Council work session

    Safer Systems Approach and 700 South cycle track

    Discussed

    The Planning Department was scheduled to present the Safer Systems Approach and discuss a cycle track on 700 South.

  3. February 9, 2026 · City Council work session

    Safer systems approach and the 700 South bike lanes

    Pending

    Presentation and discussion listed on the agenda.

  4. January 13, 2026 · City Council

    Modifying the 700 South bike lanes

    Discussed

    Council Member James Harrison said residents want changes to the current layout. Staff said the project was funded mainly with Mountainland Association of Governments trail money and, because of budget limits, was built as a two-way bike facility on one side with plastic bollards rather than a curbed, trail-like design. Engineering warned that changing the design too much could jeopardize phase 2 MAG funding (2300 West toward the Jordan River), which was approved as part of a cycle-track concept. Staff showed alternative configurations and early use data and acknowledged the need for better outreach. The council asked for design options, costs and funding effects.

  5. May 6, 2025 · City Council work session

    700 South cycle track improvement options

    Discussed

    Streets staff showed options to improve the 700 South cycle track: full curb islands (about $735,000), partial concrete curbing ($445,000), partial parking stops ($165,000) or buying a curbing machine ($820,000). Painting the lanes green would cost over $1 million. Council members agreed curbing would be better than pylons; Council Member Stallings wanted more resident input before major spending, and Council Member Newall raised intersection concerns.

  6. June 14, 2022 · City Council

    Bike and Pedestrian Master Plan update

    Discussed

    Mike West updated the council on the plan and how staff intend to make it successful. In the administrative report, Planning Director Kim Struthers also updated the council on downtown signage and the cycle track on 700 South.

  7. February 1, 2022 · City Council work session

    Capital projects

    Discussed

    City Engineer Lorin Powell showed street and water storage projects. A new culinary water tank and irrigation reservoir will serve the west side, 2300 West is being designed for build-out, a signal is planned at 1100 West and Main Street, and the 700 South cycle track should be completed this year. He discussed ideas with the Peck family for Mill Pond, which could include recreation, retail and restaurants, and wants beautification there this year. Luke Seegmiller described a traffic control center for monitoring and adjusting signals, which staff want to fund in the upcoming budget.

  8. September 22, 2020 · City Council

    700 South cycle track design contract with Avenue Consultants (Resolution #2020-66)

    Approved · 5-0

    Assistant City Engineer Brad Kenison said the agreement is to design the cycle track on 700 South. The minutes give no fee.

    Moved by Council Member Koivisto, seconded by Council Member Southwick. Vote: Unanimous, 5-0

  9. September 22, 2020 · City Council

    Interlocal agreement with Mountainland Association of Governments for the 700 South cycle track (Resolution #2020-65)

    Approved · 5-0

    The council approved an interlocal agreement with MAG for the 700 South cycle track.

    Moved by Council Member Southwick, seconded by Council Member Koivisto. Vote: Unanimous, 5-0