Lehi development tracker

UAMPS Fremont solar and battery storage

Possible participation in a 49.5-megawatt solar and 198 megawatt-hour battery project; approval expected in October 2025.

In reviewStatus as of Sep 23, 2025

Type
Public project
Applicant
Lehi Power / UAMPS

In brief

UAMPS Fremont solar and battery storage appears on one recorded agenda: the City Council meeting of September 23, 2025.

Follow the money and project delivery

UAMPS Fremont solar and battery storage

In review

  1. Council action

    In review according to the dated project source. Record → · Sept. 23, 2025

  2. Money in the record

    No itemized amount linked in the records collected.

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. September 23, 2025 · City Council

    UAMPS Fremont Solar and Battery Storage Project

    Discussed

    Power Director Joel Eves described a 49.5-megawatt solar facility with 198 megawatt-hours of battery storage whose cost is close to Lehi's blended wholesale rate. The power purchase agreement means the city pays only for energy delivered. Timing allows use of investment tax incentives that expire in July 2026. The council planned to consider approval in October.