2100 North freeway (Mountain View Corridor to I-15)
UDOT is building 2.8 miles of new freeway on 2100 North to create a nonstop freeway-to-freeway link between I-15 and Mountain View Corridor, which it estimates will save east-west commuters about 12 minutes each way at peak. The design calls for 14 new bridges, two pedestrian bridges and about 2 miles of shared-use paths. Right-of-way acquisition ran from 2025 to late fall 2025 and a design-build contractor was selected in late 2025; groundbreaking was March 18, 2026. It is the largest piece of a nearly $1.4 billion state investment in northwest Utah County.
Under construction
- Type
- Road project
- Run by
- UDOT
- Cost
- $621.0 million
- Location
- 2100 North (SR-194) in Lehi from Mountain View Corridor/Redwood Road to I-15, about 2.8 miles, including a new I-15 interchange and the Jordan River crossing
- Contractor
- Ralph L. Wadsworth Construction with W.W. Clyde & Co. (per W.W. Clyde)
- Paid for by
- State (UDOT); part of a nearly $1.4B northwest Utah County program
- Schedule
- Construction spring 2026 to late 2028
- UDOT broke ground; $621M project expected to run through late 2028.
- City Council: UDOT agreement for Jordan River pedestrian bridge (Resolution 2026-13)
- City Council: UDOT agreement for shared use path (Resolution 2026-14)
- City Council: Pre-council: term limits, Ivory Innovations lease and ice center feasibility study
- City Council: UDOT master agreement for utilities in the 2100 North project (Resolution 2025-58)
In brief
2100 North freeway (Mountain View Corridor to I-15) appears on 5 recorded agendas, from the City Council meeting of November 12, 2024 to the City Council meeting of March 10, 2026.
On record, it was approved 5 times and tabled once.
The most recent decision was tabled at the City Council meeting of March 10, 2026.
The most recent agenda collected for it, the City Council meeting of March 10, 2026, listed it with no result recorded.
Updates
March 18, 2026
UDOT broke ground; $621M project expected to run through late 2028. Source
Follow the money and project delivery
2100 North freeway (Mountain View Corridor to I-15)
- Council action
Approved: UDOT master agreement for utilities in the 2100 North project (Resolution 2025-58) · Approved minutes Record → · Aug. 26, 2025
- Money in the record
contract: $170,000 — Estimated cost of asphalt trail connection Record → · July 22, 2025
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
March 10, 2026 · City Council
UDOT agreement for Jordan River pedestrian bridge (Resolution 2026-13)
Pending
Resolution 2026-13 would approve an agreement with UDOT for design, construction and maintenance of a pedestrian bridge over the Jordan River as part of the 2100 North freeway project.
March 10, 2026 · City Council
UDOT agreement for shared use path (Resolution 2026-14)
Pending
Resolution 2026-14 would approve an agreement with UDOT for design, construction and maintenance of a shared use path as part of the 2100 North freeway project.
March 10, 2026 · City Council
Pre-council: term limits, Ivory Innovations lease and ice center feasibility study
Tabled
Pre-council discussion items were a draft ordinance on mayor and council term limits, a lease with Ivory Innovations for the Literacy Center, and a proposal for an ice center feasibility study. UDOT also presented an update on the 2100 North freeway and Pioneer Crossing flex lanes. The Lehi Free Press reported the council chose not to pursue term limits for now and asked City Attorney Ryan Wood to research a possible 2027 ballot referendum; no formal vote was reported. A $33,000 ice center feasibility study was held for a vote in two weeks.
August 26, 2025 · City Council
UDOT master agreement for utilities in the 2100 North project (Resolution 2025-58)
Approved · 5-0
Kenison said the key change is a technical modification to Exhibit E on settlement criteria for utility crossings under the freeway. UDOT is receiving bids, with a contractor expected in late October or early November.
July 22, 2025 · City Council
UDOT master agreement for utility work on the 2100 North project (Resolution 2025-50)
Approved · 5-0
Kenison said the agreement sets design criteria for city utilities within UDOT's project. UDOT's Matt Parker said the current work ends east of Redwood Road in early spring, when the 2100 North project begins; proposals are due just after Labor Day. He said a Pioneer Crossing contractor starts in about a month with completion by the end of next summer. A pedestrian bridge over SR-92 is a standalone project with an estimated cost of $7 million, for which alternative funding is sought.
July 22, 2025 · City Council
UDOT supplemental agreement for utility stubs across the freeway (Resolution 2025-51)
Approved · 5-0
Kenison and Parker said the agreement lets the city stub master-plan water, sewer, irrigation and storm drain lines across the freeway before surrounding structures are built, by adding bid items to UDOT's original contract rather than change orders. The work will be competitively bid and council can review it.
July 22, 2025 · City Council
UDOT agreement for trail connection through Holbrook Park 2 (Resolution 2025-53)
Approved · 5-0
The asphalt trail would connect the Jordan River pedestrian bridge to Waterbury Drive, replacing trails now on UDOT bridges that are being removed. The project is estimated at $170,000.
July 22, 2025 · City Council
UDOT agreement for access road from 2100 North and Thanksgiving Way to park-and-ride (Resolution 2025-54)
Approved · 5-0
Under UDOT's current design the Hadco access would become right-in, right-out, so the city and UDOT agreed to an additional access to Thanksgiving Way if that design is selected. Costs would be shared with Hadco as a shared access. The connection would improve park-and-ride access, which the project prioritizes; the project may not happen, depending on the design chosen.
March 4, 2025 · City Council work session
UDOT update: 2100 North project
Discussed
UDOT's Andrew Jordan said the 2100 North project adds freeway lanes between the existing frontage roads, with grade separations at key cross streets, shared-use path improvements and a Jordan River crossing with a grade separation tied to the city trail network. The council discussed noise wall analysis and aesthetics, and preferred not to include optional betterments such as upgraded fencing because of their cost to the city.
November 12, 2024 · City Council
North Lehi transportation system
Discussed
Traffic Engineer Luke Seegmiller and the mayor reported on a meeting with UDOT, including Director Carlos Braceros, about the proposed freeway-to-freeway connector between I-15 and Mountain View Corridor. A new alternative, 4b, aligns better with existing interchanges and could reduce traffic on Porter Rockwell Road and 2100 North. The mayor said UDOT gave serious consideration to the city's traffic projections. Bike lanes and pedestrian paths were also highlighted.