American Fork development tracker

Lakeshore Landing

Lakeshore Landing is a transit-oriented subdivision area along 900 West. On Oct. 14, 2025 the council voted unanimously to adopt an ordinance vacating a leftover strip of excess right-of-way on 900 West at about 350 South, which had been left out of an earlier 2021 vacation, so the road width matches the rest of 900 West.

ApprovedStatus as of Oct 14, 2025

Type
Subdivision
Location
Area of 900 West 350 South
Homes
204
  1. Oct 14, 2025City Council: Partial right-of-way vacation at about 350 South 900 West (Lakeshore Landing)
  2. Mar 25, 2025City Council: Partial right-of-way vacation, about 350 South 900 West (Lakeshore Landing)
  3. Dec 10, 2024City Council: Four escrow agreements, The Flats at Lakeshore Landing
  4. Feb 27, 2024City Council: Release of durability retainer, 900 West Phases 1.2A and 1.2B, 900 West 350 South
  5. Feb 27, 2024City Council: Release of durability retainer, Lakeshore Landing Phases 1-3, 900 West 350 South

In brief

Lakeshore Landing appears on 13 recorded agendas, from the City Council meeting of June 30, 2020 to the City Council meeting of October 14, 2025.

On record, it was approved with conditions 6 times, approved 8 times, and tabled once.

The most recent decision was approved (5-0) at the City Council meeting of October 14, 2025.

Follow the money and project delivery

Lakeshore Landing

Approved

  1. Council action

    Approved according to the dated project source. Record → · Oct. 14, 2025

  2. Money in the record

    guarantee: $128,624.76 — Escrowed system-improvement bond fees for four Flats at Lakeshore Landing plats Record → · Dec. 10, 2024

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. October 14, 2025 · City Council

    Partial right-of-way vacation at about 350 South 900 West (Lakeshore Landing)

    Approved · 5-0

    Ordinance 2025-10-25 vacated part of the 900 West right-of-way related to the Lakeshore Landing subdivision plat.

    Moved by Councilmember Carroll, seconded by Councilmember John. Vote: 5-0

  2. March 25, 2025 · City Council

    Partial right-of-way vacation, about 350 South 900 West (Lakeshore Landing)

    Tabled · 5-0

    Rocky Mountain Power has a box in the area; Ken Berg said a strip along 900 West was missed in an earlier vacation and the plat includes a utility easement. Tabled so the city can accept a utility easement before vacating.

    Moved by Councilmember Holley, seconded by Councilmember John. Vote: 5-0 to table

  3. December 10, 2024 · City Council

    Four escrow agreements, The Flats at Lakeshore Landing

    Approved · 5-0

    Escrow agreements with IMH SLC American Fork LLC covering system improvements for Block 1 Plat B, Block 2 Plat D, Block 3 Plat F and Block 4 Plat H of The Flats at Lakeshore Landing, approved by the council in September and October 2024.

    • Block 1 Plat B: $40,115.46
    • Block 2 Plat D: $25,003.00
    • Block 3 Plat F: $30,844.00
    • Block 4 Plat H: $32,662.30
    • Total: $128,624.76

    Moved by Councilmember Taylor, seconded by Councilmember Holley. Vote: 5-0

  4. February 27, 2024 · City Council

    Release of durability retainer, 900 West Phases 1.2A and 1.2B, 900 West 350 South

    Approved · 5-0

    Released $2,748,097.

    Moved by Councilmember Taylor, seconded by Councilmember Carroll. Vote: 5-0 (consent agenda; vote table omitted from minutes)

  5. February 27, 2024 · City Council

    Release of durability retainer, Lakeshore Landing Phases 1-3, 900 West 350 South

    Approved · 5-0

    Released $495,507.

    Moved by Councilmember Taylor, seconded by Councilmember Carroll. Vote: 5-0 (consent agenda; vote table omitted from minutes)

  6. October 24, 2023 · City Council

    The Flats at Lakeshore Landing Block 2 Plat D, 93 units

    Approved with conditions · 3-0

    Final plat of 2.42 acres in the TOD zone for a four-story, 93-unit building with the required 140 parking stalls.

    • Acres: 2.42
    • Units: 93
    • Parking: 140 stalls

    Moved by Council Member Kevin Barnes, seconded by Council Member Rob Shelton. Vote: 3-0; Carroll and Hunter absent

  7. October 24, 2023 · City Council

    The Flats at Lakeshore Landing Block 4 Plat H, 111 units, five stories

    Approved with conditions · 3-0

    Final plat of 1.87 acres in the TOD zone for 111 units with 167 parking stalls (7 via HOA agreement). TOD code lets the council allow one extra story where two lot types are on a plat; staff recommended four stories. Engineer Ken Berg said the new owner wants half the building at five stories (about 11 feet more) with a lobby, game room, gym, dog wash and meeting room on the ground floor, and no added units. Shelton worried amenities could later become apartments; owner's representative Roy Barti said that would require a change of use. Approved with a plat note that the building is approved at five stories.

    • Acres: 1.87
    • Units: 111
    • Parking: 167 stalls (7 via HOA agreement)
    • Height: 5 stories (lot type 7)

    Moved by Council Member Rob Shelton, seconded by Council Member Kevin Barnes. Vote: 3-0; Carroll and Hunter absent

  8. September 26, 2023 · City Council

    The Flats at Lakeshore Landing Block 1 Plat B and Block 3 Plat F

    Approved with conditions · 5-0

    Final plats of 1.56 acres at about 444 S. 920 West and 0.94 acres at about 496 S. 920 West in the TOD zone, subject to Sept. 6 planning commission conditions.

    • Acres: 1.56 and 0.94
    • Zone: TOD

    Moved by Council Member Rob Shelton, seconded by Carroll; Taylor. Vote: 5-0

  9. February 14, 2023 · City Council

    Releases of improvement guarantees and retainers

    Approved · 4-0

    1100 West 350 South roadway improvements Phase 2 durability retainer $2,048,322.48; Autumn Crest Plat E construction guarantee $361,748.20 (930 E. 1040 North); AF Crossing E1 $65,102.50 (900 W. 1000 South); AF Crossing Plat D $0 (1000 W. 1100 South); Lakeshore Landing Blocks 4-6 $0 (900 W. 560 South). Also a utility easement at 174 N. Grant Ave. and Jan. 18-Feb. 7 payments.

    Moved by Council Member Clark Taylor, seconded by Council Member Rob Shelton. Vote: 4-0; Hunter absent

  10. August 9, 2022 · City Council

    Lakeshore Landing Block 1 Plat B, Block 2 Plat D and Block 3 Plat F amended plats

    Approved with conditions · 4-0

    Amended three TOD-zone plats vested under old code allowing 16- or 20-foot alleys, widening alleys that need fire access to at least 26 feet (the 2021 standard is 32 feet). Carroll asked that alleys be treated as driveways; Fire Chief Aaron Brems said wider alleys are needed for buildings three stories or taller.

    • Zone: TOD
    • Fire access alleys: 26 ft minimum

    Moved by Councilmembers Taylor and Carroll. Vote: 4-0 each; Shelton absent

  11. June 28, 2022 · City Council

    Lakeshore Landing Block 4 Plats G and H, Block 5 Plat I, Block 6 Plat J amended plats

    Approved with conditions · 4-0

    Approved four amended plats in the TOD zone subject to June 8 Planning Commission conditions.

    • Zone: TOD

    Moved by Councilmembers Carroll and Taylor. Vote: 4-0 each; Shelton absent

  12. January 11, 2022 · City Council

    Common consent: minutes; retainer and construction guarantee releases for nine projects; payment ratification (Dec 8-Jan 4)

    Approved · 5-0

    Released durability retainers for American Fork Duplex ($820), Anderson Acres Plat B ($318.75), Doug Smith Kia addition ($830.91), North Point cul-de-sac ($6,835.43) and a single residence ($710.20), and construction guarantees for Autumn Crest Plat D ($170,946.88), Brubaker Lots 3-4 ($78,803.85), Rockwell Ranch Block 2 Phase 1 ($323,998) and Lakeshore Landing Blocks 1-3. Payments not itemized.

    Moved by Councilmember Taylor, seconded by Councilmember Shelton. Vote: 5-0

  13. June 8, 2021 · City Council

    Final plat extensions for Lakeshore Landing, Dixie Farms, AF 10 and AF PD South

    Approved · 4-0

    Extended final plat approvals in the PR-3.0 zone for Lakeshore Landing Plats A-J (900 West 350 South), Dixie Farms E-1, E-2, F-1 and F-2 (900 West 900 South), Dixie Farms Plat G (800 South 800 West), AF 10 Plats A-C (780 West 620 South) and AF PD South Plat A Conservation PUD (900 West 620 South).

    Moved by Councilmember Taylor, seconded by Councilmember Hunter. Vote: 4-0; Councilmember Carroll absent

  14. May 25, 2021 · City Council

    Partial vacation of 900 West right-of-way, 350 South to 620 South

    Approved · 5-0

    Adopted Ordinance 2021-05-24 vacating excess 900 West right-of-way for Lakeshore Landing Plats A-J after the road cross-section was narrowed from what was dedicated at annexation. No one spoke at the hearing.

    • Ordinance 2021-05-24

    Moved by Councilmember Taylor, seconded by Councilmember Shelton. Vote: 5-0

  15. June 30, 2020 · City Council

    Lakeshore Landing Plats A-J final plats

    Approved with conditions · 5-0

    Approved final plats in the transit-oriented development area; neighbors had raised infrastructure and density concerns at the Planning Commission.

    Moved by Council Member Carroll, seconded by Council Member Taylor. Vote: 5-0