Caveman Boulevard and 300 North traffic signal
New traffic signal built by Infrastructure Power Group LLC under a $116,988.58 contract awarded October 2025; reported complete by February 2026.
- Where it stands
- Completed
- Type
- Road project
- Location
- 600 East (Caveman Blvd.) and 300 North
- Applicant
- American Fork City
- Run by
- American Fork
- Schedule
- Completed February 2026
- Cost
- $260,000
Every hearing and vote
October 14, 2025 · City Council
Caveman Boulevard (600 East) and 300 North traffic signal contract
Approved · 5-0
Awarded to Infrastructure Power Group LLC for $116,988.58.