300 West waterline and infrastructure improvements (CDBG 10)

Culinary waterline and infrastructure improvements on 300 West funded by Community Development Block Grant money. The council approved the CDBG subrecipient agreement March 14, 2023 and awarded construction April 11 to low bidder Newman Construction for $698,000.

Under construction

Type
Public project
Location
300 West
Applicant
American Fork City
  1. Apr 11, 2023City Council: CDBG 10: 300 West waterline and infrastructure improvements
  2. Mar 14, 2023City Council: CDBG subrecipient agreement, culinary waterline improvements (CDBG 10)

In brief

300 West waterline and infrastructure improvements (CDBG 10) appears on 2 recorded agendas, from the City Council meeting of March 14, 2023 to the City Council meeting of April 11, 2023.

On record, it was approved 2 times.

The most recent decision was approved (4-0) at the City Council meeting of April 11, 2023.

Follow the money and project delivery

300 West waterline and infrastructure improvements (CDBG 10)

Under construction

  1. Council action

    Approved: CDBG 10: 300 West waterline and infrastructure improvements · Approved minutes Record → · April 11, 2023

  2. Money in the record

    contract: $698,000 — CDBG 10 300 West waterline and infrastructure improvements Record → · April 11, 2023

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. April 11, 2023 · City Council

    CDBG 10: 300 West waterline and infrastructure improvements

    Approved · 4-0

    Taylor noted a $42,000 gap between Newman and the next bid and a $90,000 spread among other bids; Bunker said that in a public bid the city must take the low bidder unless it can be disqualified, and the contractor must post a bond.

    • Low bidder; next bid about $42,000 higher

    Moved by Council Member Kevin Barnes, seconded by Council Member Rob Shelton. Vote: 4-0; Carroll absent

  2. March 14, 2023 · City Council

    CDBG subrecipient agreement, culinary waterline improvements (CDBG 10)

    Approved · 5-0

    Agreement with Utah County for CDBG funding of the 300 West waterline project; amount not stated.

    Moved by Council Member Kevin Barnes, seconded by Council Member Ryan Hunter. Vote: 5-0