Culinary waterline and infrastructure improvements on 300 West funded by Community Development Block Grant money. The council approved the CDBG subrecipient agreement March 14, 2023 and awarded construction April 11 to low bidder Newman Construction for $698,000.

Where it stands
Under construction
Type
Public project
Location
300 West
Applicant
American Fork City

Every hearing and vote

  1. March 14, 2023 · City Council

    CDBG subrecipient agreement, culinary waterline improvements (CDBG 10)

    Approved · 5-0

    Agreement with Utah County for CDBG funding of the 300 West waterline project; amount not stated.

    Moved by Council Member Kevin Barnes, seconded by Council Member Ryan Hunter. Vote: 5-0

  2. April 11, 2023 · City Council

    CDBG 10: 300 West waterline and infrastructure improvements

    Approved · 4-0

    Taylor noted a $42,000 gap between Newman and the next bid and a $90,000 spread among other bids; Bunker said that in a public bid the city must take the low bidder unless it can be disqualified, and the contractor must post a bond.

    • Low bidder; next bid about $42,000 higher

    Moved by Council Member Kevin Barnes, seconded by Council Member Rob Shelton. Vote: 4-0; Carroll absent