Public works facility
New public works building (Phase 1, north side of the 200 North campus) financed with Local Building Authority lease revenue bonds. The council authorized up to $50 million on Dec. 9, 2025, then on Jan. 13, 2026 capped the bonds at $40 million (staff had sought $45.25 million) after Councilmembers Holley and Taylor objected to a 45,000-square-foot design. Phase 2 for south-side garages would need a separate bond. WPA Architecture was proposed as designer in July 2026.
- Where it stands
- Approved
- Type
- Public project
- Location
- 275 E. 200 North
- Applicant
- American Fork City
Every hearing and vote
February 20, 2025 · City Council work session
General plan, station area plan and department outlooks
Discussed
Population grew from 33,337 (2020) to about 45,335 with 4,873 new units. Police face wage competition and space; fire apparatus costs up 50-100%, a new station needs 15 employees, and Station 51 needs about 4,000 sq. ft. or Station 53 sooner; public works needs space and has a water rights application facing four protests. GO bond capacity is largest but requires a vote.
December 9, 2025 · City Council
Public hearing on Local Building Authority lease revenue bonds
No action
Royce Shelley questioned whether the full $50 million was necessary. Mayor Frost said the building would not be a 'big box' and the final cost was expected to be lower.
December 9, 2025 · City Council
Lease revenue bond parameters resolution (council and Local Building Authority)
Approved · 5-0
Municipal advisor Matthew Dugdale and bond counsel Brandon Johnson presented a parameters resolution allowing up to $50 million, with a competitive sale planned Jan. 14 and closing Feb. 5; proceeds would cover design, land, furniture and equipment. Carroll, Taylor and Holley said they lacked project information; Taylor worried a set amount becomes a spending floor. Councilmember Hunter disclosed that his employer was awarded the Fire Station 52 project before he joined the council and said he would abstain in a similar situation; he urged CM/GC or design-build flexibility. A clause saying the council had reviewed plans was removed. Resolution 2025-12-28R passed on condition the council approve the final bond amount before issuance; the LBA board then adopted Resolution 2025-BA-03R. (On Jan. 13, 2026 the cap was set at $40 million.)
- Maximum: $50 million
- Municipal advisor: Matthew Dugdale
- Bond counsel: Brandon Johnson
- Hunter's employer built Fire Station 52 (disclosed)
January 13, 2026 · City Council
Ratifying lease revenue bonds for public works facility; maximum set at $40 million
Approved · 5-0
Public Works Director Sam Kelly said about 10 staff lack offices and bays are short, comparing needs with Orem. The Dec. 9 resolution authorized up to $50 million; staff recommended $45.25 million. Councilmember Holley said the 45,000-square-foot design is too big, favoring 25,000-30,000 square feet and a bond under $35-40 million; Taylor initially did not support the bond without a work session; John warned delays raised the irrigation system's cost from under $8 million to $47 million; Hunter backed a $40 million cap with hard bidding and add alternates. Phase 1 excludes the south-side garages, which need a separate later bond. Municipal advisor Mr. Dugdale targeted a Jan. 22 pricing date; the lease revenue bonds are rated AA2 and the city's rating rose to AA1. Resolution 2026-01-03R set the maximum at $40 million; any unused proceeds could go to property acquisition across the street.
- Original authorization: $50 million (Dec. 9, 2025)
- Staff recommendation: $45,250,000
- Approved maximum: $40,000,000
- Pricing target: Jan. 22, 2026
March 31, 2026 · City Council work session
Fiscal 2027 Fitness Center, road CIP, impact fee and Local Building Authority funds
Discussed
Finance Director Anna Montoya said there is no plan for a full Fitness Center renovation or bond; the general fund subsidizes about 35% of its operations. Road CIP projects include the 700 North extension (construction FY2027), the 200 South/300 West roundabout (MAG), the Pony Express Corridor (city's 50% MAG match), the 1100 South/100 East intersection and Lakeshore Drive Phase 1. Councilmember Hunter urged a study of a transportation utility fee (about $50,000); Carroll worried about residents' ability to pay. Park impact fees fund the Art Dye Trail (with a MAG grant) and Lakeview Park on 620 South (preliminary $4 million). Police impact fees fund an evidence building and third-floor police building improvements (about $1.8 million). Local Building Authority lease revenue bonds for the public works facility were issued in January rather than March, saving about $1.2 million; proceeds total about $40 million.
- Public works facility LBA lease revenue bonds: about $40 million, issued January 2026; about $1.2 million saved
- Lakeview Park (620 South): preliminary $4 million
- Police evidence building/3rd floor: about $1.8 million
- Transportation utility fee study: about $50,000 (not decided)
July 14, 2026 · City Council
Architectural services for new public works building
Pending
Award of design services for the planned public works facility at 275 East 200 North to WPA Architecture, the top-scored proposer, for $589,900. The city plans to hire a construction manager/general contractor later.
- Amount: $589,900
- Site: 275 E. 200 North
- Bid/proposal tabulation: RFP AF20260001; 4 scored proposals: Think Architecture 79.2, WPA Architecture 79.1, Place Collaborative 75.4, Method Studio 73.7; staff recommended WPA
August 18, 2026 · City Council work session
Bond update from Stifel
Discussed
Matt Dugdale of Stifel said American Fork holds an AA-1 general obligation rating and outperforms national medians on debt and reserve measures. Because the public works facility bonds were sold in January before interest rates rose, he estimated the city avoided about $2.5 million in extra cost over the bonds' life, nearly $89,000 a year in higher payments, and about $1.5 million less in proceeds.
- Rating: AA-1
- Estimated savings from January sale: ~$2.5 million over term