American Fork development tracker

100 West improvements, 100 North to 700 North

Phase 1 replaces utilities under 100 West from 100 North to 700 North: new water lines, sewer pipe replacement on certain blocks and storm-drain improvements. Work next to Shelley Elementary was scheduled between May 26 and Aug. 1. Phase 2 in 2027 adds curb, gutter, sidewalk and roadway improvements. An earlier segment, 100 West from 300 South to 700 South, was rebuilt with water-line replacement and completed in September 2025 for $1.96 million.

Where it stands
Under construction
Type
Road project
Location
100 West, 100 North to 700 North
Run by
American Fork
Schedule
Phase 1 (utilities) 2026; Phase 2 (surface) 2027

Updates

  1. October 14, 2026

    City lists Phase 1 budget at $3M-$4M and the project as out to bid for construction. Source

Every hearing and vote

  1. March 18, 2025 · City Council work session

    FY2026 water, sewer, storm drain and sanitation funds

    Discussed

    Culinary: service charges up 3% with no rate change yet; $7.9 million capital (down $2 million) incl. waterline replacements on 100 West, 100 East, 200 West and 300 West (CDBG), 700 North connection, Racetrack well, mobile generator; capital exceeds revenue, drawn from reserves pending rate study; new 0.7 FTE meter specialist for monthly meter reads; TOD well (impact fees). Irrigation: deficit pending rate study; grant-funded recycled water project held up at the state engineer, grant expires December 2026. Sewer: 15% TSSD pass-through Jan. 1, 2026 (TSSD raised 40% two years earlier and 15% last year), about $5/month per home, $10 for county parcels. Storm drain: rate increase justified by state mandates and five-year plan. Sanitation: 3.5% contract escalator could be absorbed from reserves.

    • Culinary capital: $7.9 million
    • TSSD increase: 15% on Jan. 1, 2026
  2. October 21, 2025 · City Council work session

    Bicycle lanes and Bicycle and Pedestrian Master Plan

    Discussed

    Community Services Director Derric Rykert said the plan dates to 2013 and will be updated through the Parks and Recreation Committee. City Engineer Ben Hunter said 100 West (about 40 feet curb to curb) got 5-foot bike lanes with parking moved to one side. Members questioned the lime-green paint used in the TOD and on 620 South near Harbor Village and Stone Creek, which is peeling and growing weeds; Hunter wanted maintenance costs and preferred spending on sidewalks such as the 200 South frontage road link between 100 East and 100 West. Taylor and Holley raised e-scooter speeds of 25-30 mph on trails. Assistant City Administrator Camden Bird said the plan connects 100 West to the Boat Harbor, Utah Lake and the Murdock Canal.

    • Riverwalk-Murdock Canal trail: spring 2026, MAG funded
  3. April 14, 2026 · City Council

    100 West road rehabilitation, 100 North to 700 North, utilities Phase 1

    Approved · 4-0

    Awarded to Newman Construction Inc. for $2,315,000 plus a $231,500 contingency. Councilmember Hunter questioned the spread between the low bid (about $2.3 million) and high bid (about $3.9 million); Public Works Director Sam Kelly said staff checked the bid tabulation and references, the second-lowest bid was within about $40,000, and he knew the contractor's work on an Orem pipeline. Final paving is expected the following year.

    • Contract: $2,315,000
    • Contingency: $231,500
    • Bids ranged about $2.3 million to $3.9 million; second-low within about $40,000
    • Repeat winner: Newman Construction also won the 200 S./300 W. roundabout the same night

    Moved by Councilmember Holley, seconded by Councilmember Carroll. Vote: 4-0; Councilmember Taylor absent

  4. April 28, 2026 · City Council work session

    Fiscal 2027 general fund, capital projects, fleet and Fitness Center budgets

    Discussed

    Street operations move to a new general fund roads fund. About $3.4 million is programmed for road capital work (overlays, crack seal, microsurfacing, slurry, 100 West, parts of Water Road, 100 East, and King Street), with total road spending about $6.5 million excluding impact fees, plus a new traffic study. $4 million is earmarked for Fitness Center improvements; its general fund subsidy stays about 35% of operating costs. Community Services capital totals about $4.9 million, including about $120,000 for playgrounds, Art Dye Park fencing and shade sails, a cremation niche project and the annual Fox Hollow contribution. Public safety equipment about $140,000; a boom lift and trailer about $90,000. Fleet: eight police vehicles (two for new officers), $500,000 to start a fire apparatus replacement program, and a shift from leasing to buying with cash. A long-dormant electronic billboard earmark is still carried forward. Members debated whether to raise property taxes amid residents' cost pressures.

    • Road capital: about $3.4 million; total roads about $6.5 million
    • Fitness Center improvements: $4 million
    • Community Services capital: about $4.9 million
    • Fire fleet replacement start: $500,000
    • 2020 ladder truck lease retires FY2028
  5. June 23, 2026 · City Council

    Interim budget for fiscal 2026-27

    Approved · 5-0

    Finance Director Anna Montoya presented the interim FY2027 budget, which includes a proposed 9% property tax increase ($660,000 a year) earmarked to partly staff a temporary third fire station (Station 53) in the Lakeview area; the money is held separately until the Aug. 11 Truth in Taxation hearing and final budget. Councilmember Tim Holley argued firefighter positions should be funded regardless of the tax outcome and that wage increases and other discretionary items should be cut first; other members said the final budget can be reshaped after the hearing. The budget message lists $15.7 million in road work, including the 700 North extension, Lakeshore Drive Phase 1, a 300 West/200 South roundabout and 100 West improvements.

    • Resolution No. 2026-06-26R
    • Proposed tax increase: 9%, about $660,000/yr, about $33/yr for average home
    • Fire department added cost FY2027: $1.8 million (budget message)
    • Fitness center repairs: $4,000,000 from general fund balance (reduces fund balance from 35% to 25%)
    • Road projects: 700 North extension 100 E-200 E $2,589,681; Lakeshore Drive Phase 1 $3,720,000; 300 West/200 South roundabout $780,000; 1100 South/100 East intersection $775,000; 100 West 100 N-700 N $1,150,000; overlay/microsurface/crack seal/slurry $3,985,000
    • Other capital: Lakeview Park $4M; Art Dye Trail $1.565M; police 3rd-floor expansion $1.5M; waterlines $7.2M; Boley Well $1.1M; Dixie Well $7.12M; sewer lining $1.5M; storm drain/curb $2.6M; public works facility $40M
    • Patriot Station CRA: $33 million bond-financed 200 South widening; first phase Frontage Road to 570 West done

    Moved by Councilmember Taylor, seconded by Councilmember Carroll. Vote: 5-0