Timp Point
Edge Homes residential development: Phase 1 (60 units), Phase 2 (80 condominium units) and Phase 3 (60 units, final approval May 25, 2021).
- Where it stands
- Approved
- Type
- Subdivision
- Location
- About 3300-3350 W. 2100 North and Hardman Way
- Homes
- 200
- Applicant
- Edge Homes
Every hearing and vote
May 26, 2020 · City Council
Timp Point concept plan, 200 lots
Approved with conditions · 5-0
Discussed with item 3. Watson said an access could be added to address a block-length exception, and surface materials and color schemes would vary; Mayor Johnson wanted more variation. Koivisto again said she voted yes because of the developer's vested rights.
- Lots: 200
September 22, 2020 · City Council
Timp Point preliminary subdivision
Approved with conditions · 4-1
The council granted preliminary approval to a 200-unit residential development. Brandon Watson represented the applicant. Council Member Koivisto voted no.
- Units: 200
December 8, 2020 · City Council
Timp Point Phase 1 final subdivision, 60 units, about 3350 W. 2100 North
Approved · 5-0
Final approval for a 60-unit residential development.
- Units: 60
January 12, 2021 · City Council
Timp Point Phase 2 final subdivision, 80 condominium units, about 3300 W. 2100 North
Approved · 5-0
Final approval for an 80-unit condominium development represented by Edge Homes.
- Applicant: Edge Homes
- Units: 80
May 25, 2021 · City Council
Timp Point Phase 3 final subdivision, 60 units, about 3300 W. Hardman Way
Approved · 4-0
Final approval for a 60-unit residential development.
- Units: 60