Eagle Mountain development tracker

Enyo Battery property rezone

About 160 acres at 500 East and 100 North (parcel 59:068:0004) rezoned from Airpark to Agriculture on Sept. 3, 2024 at the request of the owner's representative, Lake Mountain Land Company. A separate battery storage application covers parcel 18 of the Eagle Mountain Properties area, and an alternative energy code amendment was discussed Oct. 15, 2024.

Where it stands
Approved
Type
Zone change
Location
500 East and 100 North
Size
160 acres

Every hearing and vote

  1. September 3, 2024 · City Council

    Enyo Battery property rezone, about 160 acres

    Approved · 5-0

    The rezone changes parcel 59:068:0004 at 500 East and 100 North from Airpark to Agriculture. Christine Mikell of Lake Mountain Land Company spoke for the owner and no one else commented.

    • Acres: about 160
    • Zone: Airpark to Agriculture

    Moved by Council Member Donna Burnham, seconded by Council Member Rich Wood. Vote: 5-0

  2. January 21, 2025 · City Council

    Energy-related amendments to Title 17 (battery storage, natural gas, small modular reactors, solar)

    Tabled · 5-0

    Planning Director Brandon Larsen and Economic Development Director Evan Berrett presented definitions for energy uses, an agricultural zone use, permitted uses in the RTI overlay, special-use standards for battery storage, natural gas plants and small modular reactors, and solar requirements in Chapter 17.15. The hearing ran from 8:50 to 10:15 p.m. More than 20 residents and others spoke, along with representatives of Enyo, a university research official, the Utah San Rafael Energy Lab and the Eagle Mountain Nature and Wildlife Alliance; nine written comments were also submitted. The council voted unanimously to table the ordinance, and the mayor will schedule a town hall with questions and answers on energy.

    Moved by Council Member Rich Wood, seconded by Council Member Brett Wright. Vote: 5-0

  3. March 4, 2025 · City Council

    Enyo development agreement for battery storage, solar and a possible natural gas plant

    Approved with conditions · 4-1

    Enyo Energy, an independent power company, proposed battery storage, solar and possibly a natural gas plant on six parcels (59:068:0005, 0002 and 0004 and 59:084:0010, 0009 and 0007), partnering with local data centers and Rocky Mountain Power. Principal Christine Mikell addressed the council, and City Attorney Marcus Draper said this is a new agreement, not an amendment. The council approved it with the maximum power pole height revised to 175 feet, as Enyo requested. Gray said the city should be a good partner but some terms needed tightening.

    • Applicant: Enyo Energy
    • Parcels: 59:068:0005, 0002, 0004; 59:084:0010, 0009, 0007
    • Condition: power pole height 175 feet

    Moved by Council Member Brett Wright, seconded by Council Member Rich Wood. Vote: 4-1; Gray voted no