Enyo Energy development agreement
A new development agreement with Enyo Energy for battery storage, solar and possibly a natural gas plant on six parcels, partnering with local data centers and Rocky Mountain Power. The council approved it Mar. 4, 2025 4-1 with a 175-foot maximum power pole height.
- Where it stands
- Approved
- Type
- Development agreement
- Applicant
- Enyo Energy
Every hearing and vote
March 4, 2025 · City Council
Enyo development agreement for battery storage, solar and a possible natural gas plant
Approved with conditions · 4-1
Enyo Energy, an independent power company, proposed battery storage, solar and possibly a natural gas plant on six parcels (59:068:0005, 0002 and 0004 and 59:084:0010, 0009 and 0007), partnering with local data centers and Rocky Mountain Power. Principal Christine Mikell addressed the council, and City Attorney Marcus Draper said this is a new agreement, not an amendment. The council approved it with the maximum power pole height revised to 175 feet, as Enyo requested. Gray said the city should be a good partner but some terms needed tightening.
- Applicant: Enyo Energy
- Parcels: 59:068:0005, 0002, 0004; 59:084:0010, 0009, 0007
- Condition: power pole height 175 feet