Eagle Mountain development tracker

Mid-Valley Road feasibility and extension

A feasibility study by Avenue Consultants of four possible eastbound alignments of Mid-Valley Road through Hidden Valley, with right-of-way being purchased along the corridor.

Approved

Type
Road project
  1. Sep 15, 2026City Council: Consent agenda: Midvalley Road change orders, Spring Run Plaza site plans, lobbying agreement…
  2. Jul 30, 2026City Council: Lake Mountain Corridor (formerly Mid Valley Road) study
  3. May 5, 2026City Council: Consent agenda: bond releases, change orders, lobbying contract, fireworks, fee reduction and…
  4. Dec 16, 2025City Council: Consent agenda: bond release, minutes and right-of-way agreements
  5. Nov 18, 2025City Council: Mid Valley Road feasibility study (work session)

In brief

Mid-Valley Road feasibility and extension appears on 7 recorded agendas, from the City Council meeting of March 4, 2025 to the City Council meeting of September 15, 2026.

On record, it was approved once and approved with conditions 2 times.

The most recent decision was approved with conditions (3-0) at the City Council meeting of September 15, 2026.

Follow the money and project delivery

Mid-Valley Road feasibility and extension

Approved

  1. Council action

    Approved with conditions: Consent agenda: Midvalley Road change orders, Spring Run Plaza site plans, lobbying agreement and reimbursement agreement · Approved minutes Record → · Sept. 15, 2026

  2. Money in the record

    change-order: amount not given — Change orders #6 and #7, 2025 Midvalley Road extension; contract: amount not given — Lobbying services; payment: amount not given — Reimbursement agreement Record → · Sept. 15, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. September 15, 2026 · City Council

    Consent agenda: Midvalley Road change orders, Spring Run Plaza site plans, lobbying agreement and reimbursement agreement

    Approved with conditions · 3-0

    Items were change orders #6 and #7 for the 2025 Midvalley Road extension, minutes of September 1, site plans for Spring Run Plaza Lots 1 and 2 (Lot 2 with Planning Commission Condition 2 requiring the shared parking and maintenance agreement to be filed with the site plan application), a lobbying services agreement with Utah Public Solutions LLC, and a reimbursement agreement with Spring Run Parkway Partners II, LP. No amounts are stated.

    Moved by Council Member Brett Wright, seconded by Council Member Craig Whiting. Vote: 3-0

  2. July 30, 2026 · City Council

    Lake Mountain Corridor (formerly Mid Valley Road) study

    Discussed

    Participants reviewed alignments, grades, feasibility and estimated costs (no figures stated). Property representatives raised concerns about impacts to existing and planned development and suggested alignments farther south. The group discussed more traffic modeling and further evaluation of alternatives before choosing a preferred option.

  3. May 5, 2026 · City Council

    Consent agenda: bond releases, change orders, lobbying contract, fireworks, fee reduction and HVAC screening

    Approved with conditions · 5-0

    Items included bond releases (Overland Village 2 Phase A Plat 10 into warranty; Antelope Meadows Phase B Plat 5 and Browns Meadow Plat 1 out); change order #2 for the Belle Street booster power conduit and SCADA and change order #5 for the Mid Valley West extension; a professional services agreement with Stokes Strategies for lobbying; firework restrictions; a reduced plan review fee for QTS Buildings 4 and 5; extended construction hours for BHI Construction, Peckham Asphalt Paving and the Williams Companies power plant; and the multifamily HVAC screening ordinance (17.72.040) with changes discussed in the work session, which the minutes do not specify. No amounts are stated.

    Moved by Council Member Melissa Clark, seconded by Council Member Zachory Huish. Vote: 5-0

  4. December 16, 2025 · City Council

    Consent agenda: bond release, minutes and right-of-way agreements

    Approved · 5-0

    Items were the Eagle Point Townhomes Plat C bond release (out of warranty), minutes, an Eagle Quest LLC right-of-way agreement and a ratification of a Mid Valley Road right-of-way agreement with a landowner. No amounts are stated.

    Moved by Council Member Rich Wood, seconded by Council Member Melissa Clark. Vote: 5-0

  5. November 18, 2025 · City Council

    Mid Valley Road feasibility study (work session)

    Discussed

    Assistant City Engineer David Salazar and Kevin Croshaw of Avenue Consultants said the study evaluated alignments, traffic demand, rights-of-way, utilities, environmental impacts and construction costs, and tested cost-effectiveness and consistency with the transportation master plan. No cost figures are stated.

  6. May 6, 2025 · City Council

    Mid-Valley Road feasibility alignment (work session)

    Discussed

    Kevin Croshaw of Avenue Consultants presented an updated alignment with higher design speeds and reduced grades.

  7. March 4, 2025 · City Council

    Mid-Valley Road feasibility study (work session)

    Discussed

    Avenue Consultants presented four possible eastbound alignments through Hidden Valley. Council members weighed project cost, property impact, travel time, aesthetics and maintainability and named travel time and cost as key factors.