Replacement of culinary water line and a sewer pipe along Alpine Highway. A first bid of $3.8 million in 2022 was rejected; the rebid drew several bids and the council awarded it Sept. 26, 2023 to low bidder Cody Ekker Construction for $2,518,575.

Where it stands
Under construction
Type
Public project
Location
Alpine Highway
Applicant
American Fork City

Every hearing and vote

  1. September 26, 2023 · City Council

    Alpine Highway 8-inch pipeline replacement (rebid)

    Approved · 5-0

    Bunker said the project drew one bid of $3.8 million last year; the rebid drew multiple bids, with Cody Ekker Construction low at about $2.5 million. It replaces culinary water line and a sewer pipe; a two-block middle segment was done earlier. Funded in FY2023; funds roll into this year with a budget adjustment.

    • Prior bid (2022): one bid, $3.8 million
    • 2023 rebid: multiple bids, low bidder Cody Ekker Construction

    Moved by Council Member Clark Taylor, seconded by Council Member Staci Carroll. Vote: 5-0