Secondary water meter project
$1 million blanket order with Mountainland Supply for pressurized irrigation meters.
- Where it stands
- In review
- Type
- Public project
- Location
- Citywide
- Applicant
- Lehi City
Every hearing and vote
July 14, 2026 · City Council
Purchase orders
Pending
Consent approval of four purchase orders for Power and Water department work.
- PO 8399, Stuart C. Irby Co.: 6 150-kVA and 4 225-kVA pad-mount transformers for The Shops @ Skye View East buildings 4-9 and inventory, $168,600; competing quotes: WUE $175,453.33 (12-week lead), Anixter $150,873.91 (15-week lead)
- PO 8402, AC Excavation (Lehi): Spring Creek substation tie-in, 3,200 ft of 6-inch bore and related work, $184,608
- PO 8398, Stuart C. Irby Co.: 600 fault indicators at $225.50 each, $135,300; competing quotes: Anixter $242.64 each, WUE $227.29 each
- PO 8395, Mountainland Supply Co.: blanket order for pipe, valves, fittings and meters for the 2026-27 secondary (PI) meter project, $1,000,000