Lehi development tracker

Public Works storage building

Lehi proposes a concrete storage building to protect city equipment from winter weather, the first phase of public works campus expansion after a 2022 study found the campus at capacity. A $10,298,426 construction agreement with Hughes General Contractors is on the Oct. 27 consent agenda; all phases are estimated at $12.4 million. The city also bought land on Main Street near 2500 West in 2024 for future streets operations.

Where it stands
In review
Type
Public project
Applicant
Lehi City Public Works
Next hearing
City Council, Tue, Oct 27
Follow the money and project delivery

Public Works storage building

In review

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    No itemized amount linked in the records collected.

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. October 27, 2026 · City Council

    Agreement with Hughes General Contractors for the public works storage building

    Pending

    Resolution 2026-67 would approve a base-bid agreement of $10,298,426 with Hughes General Contractors, Inc. of North Salt Lake for the Public Works Storage Building (Package 02, building construction). Staff say the public works campus has reached capacity and that a 2022 study found more office and storage space is needed. The city chose a concrete building it expects to last 50 years at minimum and possibly 100 or more, and built the first phase around protecting city equipment from winter weather. Work is to finish within three months of the effective date, with monthly payment on invoice. Hughes must provide performance and payment bonds for 100 percent of the contract. The packet puts the cost of all phases at $12,411,256, including $1,518,816 for excavation and backfill the city approved earlier and $594,014 for design, engineering and construction management. The agenda lists this as a consent item.

    • Resolution: 2026-67
    • Contractor: Hughes General Contractors, Inc., North Salt Lake
    • Base bid: $10,298,426
    • Total for all phases: $12,411,256
    • Completion: within three months of the effective date
    • Bonds: performance and payment bonds for 100% of the contract amount
    • Mayor Paul Binns is authorized to sign