Published by Paul Ivinskas · Politically neutral. No endorsements.
Tuesday, November 3, 2026

Utah, on the record.

Same sections for every candidate. Every fact linked to its source. How we stay neutral →

Lehi development tracker

Spring Creek substation tie-in

$184,608 boring and conduit with AC Excavation.

In reviewStatus as of Jul 14, 2026

Type
Public project
Location
Spring Creek substation
Applicant
Lehi City Power
  1. Jul 14, 2026City Council: Purchase orders
  2. May 23, 2023City Council: New Cingular Wireless option and lease at Spring Creek Substation property (Resolution 2023-28)

In brief

Spring Creek substation tie-in appears on 2 recorded agendas, from the City Council meeting of May 23, 2023 to the City Council meeting of July 14, 2026.

On record, it was approved once.

The most recent decision was approved (5-0) at the City Council meeting of May 23, 2023.

The most recent agenda collected for it, the City Council meeting of July 14, 2026, listed it with no result recorded.

Follow the money and project delivery

Spring Creek substation tie-in

In review

  1. Council action

    In review according to the dated project source. Record → · July 14, 2026

  2. Money in the record

    purchase: $168,600 — Pad-mount transformers for The Shops @ Skye View East (buildings 4-9) and inventory; purchase: $184,608 — Spring Creek substation tie-in boring and conduit; purchase: $135,300 — 600 fault indicators; purchase: $1.00 million — Blanket order for secondary (pressurized irrigation) meter project materials, FY2026-27 Record → · July 14, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. July 14, 2026 · City Council

    Purchase orders

    Pending

    Consent approval of four purchase orders for Power and Water department work.

    • PO 8399, Stuart C. Irby Co.: 6 150-kVA and 4 225-kVA pad-mount transformers for The Shops @ Skye View East buildings 4-9 and inventory, $168,600; competing quotes: WUE $175,453.33 (12-week lead), Anixter $150,873.91 (15-week lead)
    • PO 8402, AC Excavation (Lehi): Spring Creek substation tie-in, 3,200 ft of 6-inch bore and related work, $184,608
    • PO 8398, Stuart C. Irby Co.: 600 fault indicators at $225.50 each, $135,300; competing quotes: Anixter $242.64 each, WUE $227.29 each
    • PO 8395, Mountainland Supply Co.: blanket order for pipe, valves, fittings and meters for the 2026-27 secondary (PI) meter project, $1,000,000
  2. May 23, 2023 · City Council

    New Cingular Wireless option and lease at Spring Creek Substation property (Resolution 2023-28)

    Approved · 5-0

    The council approved a second option and lease with New Cingular Wireless.

    Moved by Council Member Katie Koivisto, seconded by Council Member Mike Southwick. Vote: Unanimous (5-0)