American Fork development tracker

American Fork River rehabilitation

Restoration of the river channel and road crossings with federal NRCS help. A grant-funded watershed agreement was accepted in April 2020 and Franson Civil Engineers hired for $400,000 in environmental work in October.

Approved

Type
Public project
Location
American Fork River, Public Works yard south
  1. Oct 13, 2020City Council: American Fork River rehabilitation environmental contract with Franson Civil Engineers
  2. Apr 14, 2020City Council: Watershed agreement for American Fork River rehabilitation

In brief

American Fork River rehabilitation appears on 2 recorded agendas, from the City Council meeting of April 14, 2020 to the City Council meeting of October 13, 2020.

On record, it was approved 2 times.

The most recent decision was approved (5-0) at the City Council meeting of October 13, 2020.

Follow the money and project delivery

American Fork River rehabilitation

Approved

  1. Council action

    Approved: American Fork River rehabilitation environmental contract with Franson Civil Engineers · Approved minutes Record → · Oct. 13, 2020

  2. Money in the record

    contract: $400,000 — American Fork River rehabilitation environmental/design work Record → · Oct. 13, 2020

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. October 13, 2020 · City Council

    American Fork River rehabilitation environmental contract with Franson Civil Engineers

    Approved · 5-0

    The council approved a $400,000 contract with Franson Civil Engineers for environmental work on American Fork River road and culvert crossings, mostly from the Public Works yard south, cleared through the NRCS jointly with neighboring cities. Part of the work at 200 South near the elementary school prepares for a recently funded roundabout. Shelton asked for a maintenance budget for trees and banks.

    Moved by Council Member Shelton, seconded by Council Member Christiansen. Vote: 5-0

  2. April 14, 2020 · City Council

    Watershed agreement for American Fork River rehabilitation

    Approved · 5-0

    Accepted a grant-funded watershed agreement for environmental studies needed to qualify for future grants to rehabilitate the American Fork River channel and replace box structures; no cost to the city.

    Moved by Council Member Carroll, seconded by Council Member Taylor. Vote: 5-0