American Fork development tracker

900 West microsurfacing, chip seal and restriping

Microsurfacing and restriping of 900 West, part of the city's plan to improve safety and emergency access, with temporary daytime closures. A chip seal along 900 West was completed in April 2026 for $125,000. A new culinary well (Dixie Well, $5.5M) is being drilled near the roundabout at 900 West and 620 South, with phase 1 through December 2026.

Completed

Type
Road project
Location
900 West, TOD area
Applicant
American Fork City
Run by
American Fork
Cost
$460,000
Schedule
Completed June 2026
  1. Jun 30, 2026Microsurfacing completed (city lists June 2026).
  2. Sep 3, 2024City Council work session: Parking agreements and landlord agreements in TOD area

In brief

900 West microsurfacing, chip seal and restriping appears on one recorded agenda: the City Council work session meeting of September 3, 2024.

Updates

  1. June 30, 2026

    Microsurfacing completed (city lists June 2026). Source

Follow the money and project delivery

900 West microsurfacing, chip seal and restriping

Completed

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    budget: $114,000 — Estimate: 28 parking stalls in TOD open space (option discussed); budget: $402,000 — Estimate: 134 parking stalls in TOD (option discussed) Record → · Sept. 3, 2024

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    The project record is marked completed; check its linked documents for scope and continuing costs. Record →

Every hearing and vote

  1. September 3, 2024 · City Council work session

    Parking agreements and landlord agreements in TOD area

    Discussed

    Public Works Director Sam Kelly said restriping 900 West to keep 26 feet clear for fire trucks would remove 35 stalls; options include alternating on-street parking, 28 stalls in open-space parcels (about $114,000) or 134 stalls ($402,000). The parcels are HOA open space over a TSSD easement, not city-owned. City Administrator David Bunker proposed barring future developments from charging residents for on-site parking and floated a small park on 620 South. Kelly planned microsurfacing this fall and chip seal in spring. The mayor said funding would come in next year's budget unless the council amends it.

    • 900 West restriping: 35 stalls removed
    • Option: 28 stalls in open space, ~$114,000
    • Option: 134 stalls, ~$402,000