860 East road improvements
Repaving of the middle section of 860 East using Egg Farm EDA funds; Kilgore Contracting won the contract at $267,476.30 on March 31, 2020.
Approved
- Type
- Road project
- Location
- 860 East (Egg Farm EDA, near the Lindon border)
In brief
860 East road improvements appears on one recorded agenda: the City Council meeting of March 31, 2020.
On record, it was approved with conditions once.
The most recent decision was approved with conditions (5-0) at the City Council meeting of March 31, 2020.
Follow the money and project delivery
860 East road improvements
- Council action
Approved with conditions: 860 East road improvements contract to Kilgore Contracting · Approved minutes Record → · March 31, 2020
- Money in the record
contract: $267,476.30 — 860 East road improvements (ST201903) Record → · March 31, 2020
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
March 31, 2020 · City Council
860 East road improvements contract to Kilgore Contracting
Approved with conditions · 5-0
Accepted Kilgore's bid to repave the middle section of 860 East on the east side of the Price property (Egg Farm EDA), contingent on the mayor asking the western landowner, Price, to improve its side at the same time. Shelton worried about three asphalt seams; staff said the owner rarely returned calls, the ditch, power poles and right-of-way are on private land, and bid prices are held only 30 days. RDA funds must be spent within ten years.