100 West road rehabilitation, 300 South to 700 South
FY2025 rehabilitation of 100 West between 300 South and 700 South, with utility work followed by full-depth reclamation. Awarded Feb. 25, 2025 to Geneva Rock Products for $1,922,063.50 plus a $190,000 city-held contingency. In June 2025 Public Works said the 100 West work was progressing and the city was coordinating with TSSD on paving farther south.
Under construction
- Type
- Road project
- Location
- 100 West, 300 South to 700 South
- Applicant
- American Fork City
- City Council: FY2025 road rehabilitation, 100 West from 300 South to 700 South
- City Council: State of the City address
In brief
100 West road rehabilitation, 300 South to 700 South appears on 2 recorded agendas, from the City Council meeting of January 28, 2025 to the City Council meeting of February 25, 2025.
On record, it was approved once.
The most recent decision was approved (5-0) at the City Council meeting of February 25, 2025.
Follow the money and project delivery
100 West road rehabilitation, 300 South to 700 South
- Council action
Approved: FY2025 road rehabilitation, 100 West from 300 South to 700 South · Approved minutes Record → · Feb. 25, 2025
- Money in the record
contract: $1.92 million — FY2025 road rehabilitation, 100 West 300 South-700 South (plus $190,000 contingency) Record → · Feb. 25, 2025
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
February 25, 2025 · City Council
FY2025 road rehabilitation, 100 West from 300 South to 700 South
Approved · 5-0
Public Works Director Sam Kelly said utility work comes first, with section closures during full-depth reclamation and a public information effort; the 300 West roundabout is still in design and won't overlap.
- Vendor: Geneva Rock Products
- Amount: $1,922,063.50 plus $190,000 contingency
January 28, 2025 · City Council
State of the City address
No action
PARC tax spent $1.2 million in 2024; about 80 acres of lakeside open space owned; Boat Harbor $3.8 million funded by state and county grants; fitness center expansion being studied; fire 4,751 calls, police 29,104 calls; $55,000+ mental health grant; $31 million on roads in FY2024 and almost $95 million planned; 2025 projects include Auto Mall Drive extension, sewer lining and 100 West rehabilitation; building permits down 13%; 463 businesses.
- FY2024 road spending: $31 million
- Planned roads/infrastructure: almost $95 million