Eagle Mountain development tracker

Mountainland Supply site plan

A site plan for Mountainland Supply (Wolverine Ventures) in the Rush Creek subdivision, in the Light Manufacturing/Distribution zone, discussed in the March 19, 2024 work session. Staff redlined two submittals as not meeting building material standards; the applicant offered contrasting panels and awnings.

Where it stands
Approved
Type
Site plan
Location
800 East Split Rock Drive (parcels 51:756:0108 and 51:756:0109)
Applicant
Mountainland Supply

Every hearing and vote

  1. March 19, 2024 · City Council

    Mountainland Supply site plan (work session)

    Discussed

    Stroud said two submittals were redlined as noncompliant. The site is in the Rush Creek subdivision in the Light Manufacturing/Distribution zone, and metal is allowed only as an accent outside the Sweetwater Industrial Overlay. Applicant Bert Bradford offered contrasting panels and awnings and said metal framing was ordered early to avoid a $500,000 cost increase. Wood preferred concrete masonry or tilt-up buildings. Council members were open to flat metal paneling but not corrugated metal. No vote was taken.

  2. April 16, 2024 · City Council

    Mountainland Supply site plan, 800 East Split Rock Drive

    Pending

    The consent agenda lists a site plan for Mountainland Supply on county parcels 51:756:0108 and 51:756:0109. The result is not available.

  3. September 16, 2025 · City Council

    Development agreement with Mountainland Supply

    Approved · 5-0

    City Attorney Marcus Draper and applicant Matt Cook discussed a new store in the Rush Creek Industrial development. Mountainland wants a retaining wall on the property line while city code requires a 3-foot setback; the agreement gives a legal path. The motion was delayed so staff could research a building on adjacent storage units behind the lot.

    Moved by Council Member Brett Wright, seconded by Council Member Rich Wood. Vote: 5-0