Mountainland Supply is opening a store in the Rush Creek Industrial development and needs a retaining wall on the property line, where city code requires a 3-foot setback. On Sept. 16, 2025 the council voted unanimously to approve a development agreement that allows it, after holding the vote while staff checked how the building sits next to the neighboring storage units.

ApprovedStatus as of Sep 16, 2025

Type
Site plan
Applicant
Mountainland Supply
Location
800 East Split Rock Drive (parcels 51:756:0108 and 51:756:0109)
  1. Sep 16, 2025City Council: Development agreement with Mountainland Supply
  2. Apr 16, 2024City Council: Mountainland Supply site plan, 800 East Split Rock Drive
  3. Mar 19, 2024City Council: Mountainland Supply site plan (work session)

In brief

Mountainland Supply site plan appears on 3 recorded agendas, from the City Council meeting of March 19, 2024 to the City Council meeting of September 16, 2025.

On record, it was approved once.

The most recent decision was approved (5-0) at the City Council meeting of September 16, 2025.

Follow the money and project delivery

Mountainland Supply site plan

Approved

  1. Council action

    Approved according to the dated project source. Record → · Sept. 16, 2025

  2. Money in the record

    No itemized amount linked in the records collected.

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. September 16, 2025 · City Council

    Development agreement with Mountainland Supply

    Approved · 5-0

    City Attorney Marcus Draper and applicant Matt Cook discussed a new store in the Rush Creek Industrial development. Mountainland wants a retaining wall on the property line while city code requires a 3-foot setback; the agreement gives a legal path. The motion was delayed so staff could research a building on adjacent storage units behind the lot.

    Moved by Council Member Brett Wright, seconded by Council Member Rich Wood. Vote: 5-0

  2. April 16, 2024 · City Council

    Mountainland Supply site plan, 800 East Split Rock Drive

    Pending

    The consent agenda lists a site plan for Mountainland Supply on county parcels 51:756:0108 and 51:756:0109. The result is not available.

  3. March 19, 2024 · City Council

    Mountainland Supply site plan (work session)

    Discussed

    Stroud said two submittals were redlined as noncompliant. The site is in the Rush Creek subdivision in the Light Manufacturing/Distribution zone, and metal is allowed only as an accent outside the Sweetwater Industrial Overlay. Applicant Bert Bradford offered contrasting panels and awnings and said metal framing was ordered early to avoid a $500,000 cost increase. Wood preferred concrete masonry or tilt-up buildings. Council members were open to flat metal paneling but not corrugated metal. No vote was taken.