Eagle Mountain Data Campus
A rezone to the Regional Technology and Industry Overlay for a potential data center on agricultural land near a Rocky Mountain Power substation. Approved 4-0 on Feb. 15, 2022 with water and power concerns to be handled in later agreements.
- Where it stands
- Approved
- Type
- Zone change
Every hearing and vote
February 1, 2022 · City Council
Upcoming planning items (work session)
Discussed
Planners listed Founder's Square Phase A (a 211-lot plat, formerly part of Ault Farms), a rezone to the Regional Technology and Industry Overlay for the Eagle Mountain Data Campus, and site plans for a Wendy's and three retail buildings at Marketplace.
February 15, 2022 · City Council
Eagle Mountain Data Campus rezone
Approved · 4-0
Applicant representative Corey Berg said a buyer wants to close on 1.5 acres and begin development, with the remainder staying a sod farm until developed; a site plan is expected in late April. The site is zoned Agricultural, designated Business Park/Light Industry and proposed for the Regional Technology and Industry Overlay. Burnham asked whether to wait for the overlay review and Gray cited water and power concerns but did not oppose; Jerome said Rocky Mountain Power confirmed sufficient capacity; Steve Mumford said water-use concerns would be addressed in development agreements; the overlay is scheduled to repeal in May 2022. No one spoke.
June 6, 2023 · City Council
Eagle Mountain Data Center Campus preliminary plat
Approved · 5-0
The plat has 11 lots plus a 0.06-acre city pump station lot on 490 acres. Approved on the consent agenda.
- Acres: 490
- Lots: 11 plus a 0.06-acre city pump station lot
June 3, 2025 · City Council
Consent agenda: bond releases, temporary traffic signal change order, District site plan and grant-related resolutions
Approved · 5-0
Items included the Eagle Mountain Data Center Campus subdivision bond release (into warranty) and Harmony Phase A Plat 4 (out of warranty); change order #1 with BHI for temporary traffic signals on the Pony Express Parkway and Eagle Mountain Boulevard project (amount not stated); the District at Eagle Mountain Town Center Lot 3 site plan; adoption of the Mountainland Safe Streets 2024 Safety Action Plan for federal grant eligibility; and a resolution supporting the Healthy Utah Community Initiative.
October 21, 2025 · City Council
Development agreement with Stadion, LLC (Meta) for data center expansion
Approved · 4-1
Draper said the agreement allows the data center to expand onto the adjacent property to the south, which already has the RTI overlay, sets infrastructure requirements and is largely modeled on the existing agreement. No reason for Burnham's no vote is recorded.
- Applicant: Stadion, LLC (Meta)