State Street water main replacement

Replacement of the water main and laterals under State Street ahead of UDOT's road work. The council approved a UDOT betterment agreement for 400-600 East (Feb. 14, 2023), a Horrocks Engineers design contract and a $2,362,562 construction contract to sole bidder Condie Construction for 200-500 East (May 9).

Under construction

Type
Public project
Location
State Street, 200 East to 600 East
Applicant
American Fork City
  1. May 9, 2023City Council: Horrocks Engineers design contract, State Street water main, 200 East to 500 East
  2. May 9, 2023City Council: State Street water main replacement construction contract
  3. Mar 21, 2023City Council work session: FY2024 water, sewer and storm drain funds
  4. Feb 14, 2023City Council: UDOT betterment agreement: water main on State Street and 500 East, 400 East to 600 East

In brief

State Street water main replacement appears on 3 recorded agendas, from the City Council meeting of February 14, 2023 to the City Council meeting of May 9, 2023.

On record, it was approved 3 times.

The most recent decision was approved (4-0) at the City Council meeting of May 9, 2023.

Follow the money and project delivery

State Street water main replacement

Under construction

  1. Council action

    Approved: Horrocks Engineers design contract, State Street water main, 200 East to 500 East · Approved minutes Record → · May 9, 2023

  2. Money in the record

    contract: amount not given — Engineering services for State Street water main replacement, 200 East to 500 East Record → · May 9, 2023

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. May 9, 2023 · City Council

    Horrocks Engineers design contract, State Street water main, 200 East to 500 East

    Approved · 4-0

    Engineering services agreement; the project replaces 15 service laterals along with the main so they don't fail after the road is rebuilt. Amount not stated in minutes.

    Moved by Council Member Rob Shelton, seconded by Council Member Ryan Hunter. Vote: 4-0; Taylor absent

  2. May 9, 2023 · City Council

    State Street water main replacement construction contract

    Approved · 4-0

    Condie Construction was the only bidder and came in well above the original engineer's estimate; staff reviewed options and timing given the project's complexity and recommended proceeding.

    • Bids: 1 (Condie Construction); above engineer's estimate

    Moved by Council Member Staci Carroll, seconded by Council Member Kevin Barnes. Vote: 4-0; Taylor absent

  3. March 21, 2023 · City Council work session

    FY2024 water, sewer and storm drain funds

    Discussed

    No water rate increase; the water line bond proceeds are fully received. New projects: State Street water main replacement with UDOT betterments, valve replacements, racetrack well improvements. Pressurized irrigation: no rate changes; $6.6 million state Division of Water Resources grant and $1.5 million federal grant for PI metering; 4,400 one-inch meters ordered six months earlier were arriving slowly. Water impact fee reserves about $2.6 million. Sewer: no rate increase; $700,000 for sewer lining and $800,000 for pipe bursting. Storm drain fee rising from $8.50 to $10.50 a month in January (already approved); $2.5 million in curb and gutter replacement requested. Bunker said the city will apply by Nov. 1 for water reuse with Timpanogos Special Service District.

  4. February 14, 2023 · City Council

    UDOT betterment agreement: water main on State Street and 500 East, 400 East to 600 East

    Approved · 4-0

    UDOT's contractor will replace the city water main during UDOT's road project and the city will pay; funding was set aside in capital projects a couple of years ago. Shelton raised concerns about a trail corridor on the north side, but the city doesn't control UDOT's plans. Amount not stated.

    Moved by Council Member Staci Carroll, seconded by Council Member Rob Shelton. Vote: 4-0; Hunter absent