American Fork development tracker

Hospital Well rehabilitation

Rehabilitation of one of the city's oldest and most-used culinary wells: redevelopment by Widdison Turbine Service for $160,900 (the only bid), followed by a new high-efficiency pump and motor, to be done before the 2022 irrigation season.

Approved

Type
Public project
Location
Hospital Well
Applicant
American Fork City

In brief

Hospital Well rehabilitation appears on one recorded agenda: the City Council meeting of August 24, 2021.

On record, it was approved once.

The most recent decision was approved (5-0) at the City Council meeting of August 24, 2021.

Follow the money and project delivery

Hospital Well rehabilitation

Approved

  1. Council action

    Approved: Hospital Well redevelopment contract, Widdison Turbine Service · Approved minutes Record → · Aug. 24, 2021

  2. Money in the record

    contract: $160,900 — Hospital Well redevelopment (pump pull, brush and bail, swab, pump test) Record → · Aug. 24, 2021

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. August 24, 2021 · City Council

    Hospital Well redevelopment contract, Widdison Turbine Service

    Approved · 5-0

    Awarded a contract to pull the pump, clean and redevelop the casing and pump-test the Hospital Well, one of the city's oldest and most used, to increase yield before a new pump and motor are sized. Bids were opened Aug. 17 through the state purchasing site; the tabulation shows a single bid against Horrocks Engineers' estimate of $172,800. Work is planned after irrigation season, finishing before the 2022 season, with penalties for delay.

    • Bidders: Widdison Turbine Service LLC $160,900 (only bid on tabulation)
    • Engineer's estimate (Horrocks Engineers): $172,800
    • Mobilization: $30,000

    Moved by Councilmember Taylor, seconded by Councilmember Carroll. Vote: 5-0