American Fork development tracker

CDBG Phase 9 Orchard Drive-400 East road and water line

Federally funded Community Development Block Grant project replacing culinary water lines and rebuilding Orchard Drive and 400 East. K.W. Robinson Construction won the $1,370,626.65 contract in August 2022.

Where it stands
Under construction
Type
Public project
Location
Orchard Drive and 400 East
Applicant
American Fork City

Every hearing and vote

  1. August 9, 2022 · City Council

    CDBG Phase 9 Orchard Drive-400 East road and culinary water contract

    Approved · 4-0

    Accepted K.W. Robinson Construction's bid of $1,370,626.65 for CDBG 9 Orchard-400 East road and culinary water improvements. Barnes noted federal funding; the mayor noted a required city match. The minutes do not list other bidders.

    • Contractor: K.W. Robinson Construction Inc.
    • Bid: $1,370,626.65

    Moved by Councilmember Taylor, seconded by Councilmember Hunter. Vote: 4-0; Shelton absent