Published by Paul Ivinskas · Politically neutral. No endorsements.
Tuesday, November 3, 2026

Utah, on the record.

Same sections for every candidate. Every fact linked to its source. How we stay neutral →

American Fork development tracker

CDBG Phase 9 Orchard Drive-400 East road and water line

Federally funded Community Development Block Grant project replacing culinary water lines and rebuilding Orchard Drive and 400 East. K.W. Robinson Construction won the $1,370,626.65 contract in August 2022.

Under construction

Type
Public project
Location
Orchard Drive and 400 East
Applicant
American Fork City

In brief

CDBG Phase 9 Orchard Drive-400 East road and water line appears on one recorded agenda: the City Council meeting of August 9, 2022.

On record, it was approved once.

The most recent decision was approved (4-0) at the City Council meeting of August 9, 2022.

Follow the money and project delivery

CDBG Phase 9 Orchard Drive-400 East road and water line

Under construction

  1. Council action

    Approved: CDBG Phase 9 Orchard Drive-400 East road and culinary water contract · Approved minutes Record → · Aug. 9, 2022

  2. Money in the record

    contract: $1.37 million — CDBG Phase 9 Orchard Drive-400 East road and culinary water line improvements Record → · Aug. 9, 2022

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. August 9, 2022 · City Council

    CDBG Phase 9 Orchard Drive-400 East road and culinary water contract

    Approved · 4-0

    Accepted K.W. Robinson Construction's bid of $1,370,626.65 for CDBG 9 Orchard-400 East road and culinary water improvements. Barnes noted federal funding; the mayor noted a required city match. The minutes do not list other bidders.

    • Contractor: K.W. Robinson Construction Inc.
    • Bid: $1,370,626.65

    Moved by Councilmember Taylor, seconded by Councilmember Hunter. Vote: 4-0; Shelton absent