Triumph pedestrian bridge
Pedestrian bridge project that needed a $300,000 budget amendment because costs ran above estimates, funded with road tax money.
Approved
- Type
- Public project
- Location
- Triumph Boulevard
In brief
Triumph pedestrian bridge appears on one recorded agenda: the City Council meeting of January 25, 2022.
On record, it was approved once.
The most recent decision was approved (5-0) at the City Council meeting of January 25, 2022.
Follow the money and project delivery
Triumph pedestrian bridge
- Council action
Approved: Purchase orders: Hospital Loop Road and Triumph pedestrian bridge · Approved minutes Record → · Jan. 25, 2022
- Money in the record
contract: $2.00 million — Hospital Loop Road, total project; city share $400,000, UDOT the remainder; budget: $300,000 — Budget amendment for the Triumph pedestrian bridge because costs exceeded estimates; purchase: $1.80 million — Third project over two fiscal years; not named in the minutes Record → · Jan. 25, 2022
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
January 25, 2022 · City Council
Purchase orders: Hospital Loop Road and Triumph pedestrian bridge
Approved · 5-0
Finance Director Dean Lundell explained three projects. The Hospital Loop Road is a $2 million project of which the city is responsible for $400,000 and UDOT for the rest, requiring a budget amendment. The Triumph pedestrian bridge needs a $300,000 budget amendment because costs ran higher than expected. A third item totals $1.8 million over two fiscal years. He said the city is not over budget and is using road tax money for the projects.