Lehi development tracker

Innovation Pointe

General plan change on 40 acres (Jan. 14, 4-1) and rezone of 35 acres to Commercial (March 31, 4-1); Phase 2 final subdivision of 3 commercial lots approved 3-2 on June 9, 2020 with an 11.5-foot block-length exception.

Approved

Type
Area or general plan
Size
40 acres
Location
Approximately 1441-1450 West Innovation Way
  1. Jun 9, 2020City Council: Innovation Pointe Phase 2 final subdivision, 3 commercial lots
  2. Mar 31, 2020City Council: Innovation Way zone change, 35 acres, Business Park to Commercial (Ordinance #14-2020)
  3. Jan 14, 2020City Council: Innovation Pointe general plan amendment, Business Park to Commercial (Ordinance #01-2020)

In brief

Innovation Pointe appears on 3 recorded agendas, from the City Council meeting of January 14, 2020 to the City Council meeting of June 9, 2020.

On record, it was approved with conditions 3 times.

The most recent decision was approved with conditions (3-2) at the City Council meeting of June 9, 2020, with Council Member Paige Albrecht, Council Member Katie Koivisto voting no.

Follow the money and project delivery

Innovation Pointe

Approved

  1. Council action

    Approved with conditions: Innovation Pointe Phase 2 final subdivision, 3 commercial lots · Approved minutes Record → · June 9, 2020

  2. Money in the record

    No itemized amount linked in the records collected.

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. June 9, 2020 · City Council

    Innovation Pointe Phase 2 final subdivision, 3 commercial lots

    Approved with conditions · 3-2

    Kent England, for the applicant, and Community Development Director Kim Struthers discussed a curve in the street caused by topography; England said the Hales Engineering traffic study shows the alignment works and they hope to buy land to straighten it, and Struthers said the road is not expected to carry high volume. The council approved the plan with an 11.5-foot exception to block length. Albrecht and Council Member Katie Koivisto voted no; the minutes record no reasons.

    • Lots: 3 commercial
    • Block length exception: 11.5 feet

    Moved by Council Member Mike Southwick, seconded by Council Member Paul Hancock. Vote: 3-2; Council Members Paige Albrecht and Katie Koivisto voted no

  2. March 31, 2020 · City Council

    Innovation Way zone change, 35 acres, Business Park to Commercial (Ordinance #14-2020)

    Approved with conditions · 4-1

    Kent England, for the applicant, said he was surprised the Planning Commission recommended denial after unanimously approving the general plan amendment, and thought landscape percentages caused confusion. Community Development Director Kim Struthers said the city is eliminating the Business Park zone and wants denser buildings there; the negative recommendation stemmed from lower landscaping requirements in Commercial. Wood said denying a zone change that matches the general plan needs well-founded findings and is a very high bar.

    • Acres: 35
    • Business Park → Commercial
    • Planning Commission recommendation: denial

    Moved by Council Member Chris Condie, seconded by Council Member Mike Southwick. Vote: 4-1; Council Member Katie Koivisto voted no

  3. January 14, 2020 · City Council

    Innovation Pointe general plan amendment, Business Park to Commercial (Ordinance #01-2020)

    Approved with conditions · 4-1

    Applicant representative Kent England said the request covers 40 acres, not the 16 on the agenda. Mayor Johnson said Commercial zoning allows retail such as restaurants and spreads peak traffic, while Business Park alone concentrates it. Koivisto was concerned about not knowing what would be built on the east side and about allowing a wide range of uses; Albrecht was comfortable with the school field as a buffer. The council approved the change for 40 acres with a condition that an agreement state building 3 will be an office building.

    • Acres: 40
    • Business Park → Commercial

    Moved by Council Member Chris Condie, seconded by Council Member Mike Southwick. Vote: 4-1; Council Member Katie Koivisto voted no