Ken Garff Ford Truck Center
EV charging stations at an existing dealership in the GC-2 zone, approved 7-0 April 16, 2025.
Approved
- Type
- Site plan
- Location
- 581 East 1100 South
- Size
- 7.5 acres
- Applicant
- Ken Garff
- Planning Commission: Ken Garff Truck Center EV charging stations site plan, about 581 E. 1100 South (7.5 ac…
- City Council: Ken Garff Ford Truck Center site plan (Ordinance 2022-10-48)
In brief
Ken Garff Ford Truck Center appears on 2 recorded agendas, from the City Council meeting of October 11, 2022 to the Planning Commission meeting of April 16, 2025.
On record, it was approved with conditions 2 times.
The most recent decision was approved with conditions (7-0) at the Planning Commission meeting of April 16, 2025.
Follow the money and project delivery
Ken Garff Ford Truck Center
- Council action
Approved according to the dated project source. Record → · April 16, 2025
- Money in the record
No itemized amount linked in the records collected.
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
April 16, 2025 · Planning Commission
Ken Garff Truck Center EV charging stations site plan, about 581 E. 1100 South (7.5 acres)
Approved with conditions · 7-0
Adds electric vehicle charging stations at an existing auto dealership in the GC-2 zone. Commissioner Rod Martin asked why such a project needs commission review; staff said code still requires it.
- Applicant: Ken Garff Truck Center
- Acres: 7.5
- Zone: GC-2
October 11, 2022 · City Council
Ken Garff Ford Truck Center site plan (Ordinance 2022-10-48)
Approved with conditions · 5-0
Approved a site plan for a new truck center in the GC-2 zone, subject to Sept. 21, 2022, Planning Commission conditions. Hunter joined electronically.
- Zone: GC-2