American Fork · City Council

Council signs on with STRATA Networks to begin designing citywide fiber system

October 11, 2022, 7:00 p.m. · American Fork City Hall, 31 N. Church St.

The American Fork City Council unanimously approved a master services agreement and first statement of work with STRATA Networks to start designing a city-owned fiber-optic network, to be fronted with capital projects money and repaid from a bond planned for 2023. It approved a Ken Garff Ford truck center on 1100 South, new dead-end street and temporary cul-de-sac rules, and liquor licenses for two sushi restaurants. Councilmember Staci Carroll voted against a lot consolidation between Greenwood Creek and Searle Meadows.

From the approved minutes.

Decisions at a glance

Agenda, item by item

  1. Item 2 · Presentation

    HERO award to Jay Allen

    No action

    The mayor honored the late Jay Allen, an American Fork High teacher for 46 years and Timpanogos Cave ranger for 53, declaring Sept. 26, 2022, Jay Allen Day.

  2. Item Consent 3 · Development

    Release of $17,635 construction guarantee, Crossroads at American Fork Phase 2

    Approved · 4-0 · 717 W. Main St.

    Released guarantee and accepted improvements.

    • Payment$17,635 Construction guarantee release, Crossroads at American Fork Phase 2. Paid from Developer guarantee

    Moved by Councilmember Taylor, seconded by Councilmember Barnes. Vote: 4-0 (consent agenda); Hunter absent

  3. Item Consent 4 · Development

    Release of $65,978 construction guarantee, Rockwell Ranch Block 1 Phase 2

    Approved · 4-0 · 1060 West 420 South

    Released guarantee and accepted improvements.

    • Payment$65,978 Construction guarantee release, Rockwell Ranch Block 1 Phase 2. Paid from Developer guarantee

    Moved by Councilmember Taylor, seconded by Councilmember Barnes. Vote: 4-0 (consent agenda); Hunter absent

  4. Item Consent 5 · Development

    Release of $27,121.28 durability retainer, Lake City Row sewer

    Approved · 4-0 · 620 South 860 East

    Released durability retainer.

    • Payment$27,121 Durability retainer release, Lake City Row sewer. Paid from Developer guarantee

    Moved by Councilmember Taylor, seconded by Councilmember Barnes. Vote: 4-0 (consent agenda); Hunter absent

  5. Item Action 1-2 · Other

    Liquor licenses for Tapa Sushi and Nori Sushi Bar and Grill

    Approved · 4-0 · 513 S. 500 East; 821 W. State Road

    Approved alcoholic beverage licenses for Tapa Sushi Japanese Cuisine (513 S. 500 East) and Nori Sushi Bar and Grill (821 W. State Road).

    Moved by Councilmembers Shelton and Taylor. Vote: 4-0 each; Hunter absent

  6. Item Action 3 · Contract

    Water banking agreement with Deer Park LLC, 52.638 acre-feet

    No action

    Pulled from the agenda because the agreement was not ready.

    • Water: 52.638 acre-feet
  7. Item Action 4-5b · Subdivision

    Greenwood Creek/Searle Meadows easement vacation and lot consolidation (Ordinance 2022-10-47)

    Approved · 4-1 · 685 West 1040 North and 676 West 1000 North

    Vacated a public utility easement and amended the Greenwood Creek and Searle Meadows plats to move Greenwood Creek Lot 3 into the Shin family lot in Searle Meadows (R1-12,000 zone). Councilmember Carroll objected that the consolidation leaves a fenced double-frontage lot rather than a home facing the street; Councilmember Taylor noted neighbors agreed.

    • Zone: R1-12,000

    Moved by Councilmember Shelton, seconded by Councilmember Taylor (vacation) and Councilmember Barnes (plats). Vote: 4-1 on each of three votes; Councilmember Carroll voted no. Voting no: Councilmember Staci Carroll

  8. Item Action 5c · Development

    Ken Garff Ford Truck Center site plan (Ordinance 2022-10-48)

    Approved with conditions · 5-0 · 581 East 1100 South

    Approved a site plan for a new truck center in the GC-2 zone, subject to Sept. 21, 2022, Planning Commission conditions. Hunter joined electronically.

    • Zone: GC-2

    Moved by Councilmember Taylor, seconded by Councilmember Shelton. Vote: 5-0

    Follow Ken Garff Ford Truck Center in the development tracker →

  9. Item Action 6 · City code

    Dead-end streets and temporary cul-de-sac standards (Ordinance 2022-10-49)

    Approved · 5-0

    Amended Section 15.1.100(E) on dead-end streets, revised the cul-de-sac standard drawing and created a temporary cul-de-sac drawing. Councilmember Shelton suggested adopting the International Fire Code's 750-foot temporary cul-de-sac length (allowing 17 homes rather than 15); Carroll declined to amend her motion.

    Moved by Councilmember Carroll, seconded by Councilmember Taylor. Vote: 5-0

  10. Item Action 7 · City code

    Future roadway extension (stub street) code (Ordinance 2022-10-50)

    Approved · 5-0

    City-initiated change letting the Development Services Director recommend whether a subdivision must stub streets to adjacent parcels, rather than requiring stubs to all neighboring parcels.

    Moved by Councilmember Shelton, seconded by Councilmember Barnes. Vote: 5-0

  11. Item Action 8 · Other

    Fitness Center spring floor declared surplus (Resolution 2022-10-36R)

    Approved · 5-0 · American Fork Fitness Center

    Declared the Fitness Center spring floor surplus for disposal.

    Moved by Councilmember Shelton, seconded by Councilmember Barnes. Vote: 5-0

  12. Item Action 9 · Contract

    STRATA Networks master services agreement and statement of work for city fiber

    Approved · 5-0 · Citywide

    Approved a master services agreement and Phase I statement of work with STRATA Networks to begin design of a citywide fiber-optic network; Bunker said Phase I design is about 8% of total project cost. Costs will be fronted from the capital projects fund and reimbursed from a bond expected in 2023; starting now saves six to eight months. The city keeps ownership of the design; profit-sharing is open for later negotiation. Shelton asked about micro-trenching and said a Comcast lobbyist had asked how Comcast could invest to stop the project. Carroll said she now supports it as a true public-private partnership. No dollar amount is stated in the minutes.

    • ContractAmount not given to STRATA Networks Phase I design of city fiber-optic network under master services agreement. Paid from Capital projects fund, to be reimbursed by fiber bond
    • Phase I design: about 8% of total budget
    • Future funding: fiber bond expected 2023
    • Participation by residents not mandatory

    Moved by Councilmember Taylor, seconded by Councilmember Barnes. Vote: 5-0

    Follow Citywide fiber-optic network (STRATA Networks) in the development tracker →

What residents said

Street repavingConstruction dustMunicipal fiber financial risk

No one spoke at hearings on a utility-easement vacation and surplus of the Fitness Center spring floor. Joe Garlington of Goldcrest Homes backed a hammerhead turnaround option in the cul-de-sac code. Alan Christiansen asked when his aging street would be repaved. Rio Honaker complained about construction dust near his home. Ken Sumsion warned about UTOPIA's finances, urged caution with fiber partners and said he would oppose a fiber bond door to door.