American Fork development tracker

Culinary water line project (Segments 3 and 4)

Segment 4 of the city's culinary water line project: on Feb. 28, 2023 the council unanimously awarded the 18-inch Culinary Water Line Project, Segment 4, to Condie Construction Company for $5,680,720.10.

Under construction

Type
Public project
Applicant
American Fork City
  1. Feb 28, 2023City Council: 18-inch culinary water line, Segment 4 construction
  2. Feb 16, 2023City Council work session: FY2023 capital projects and budget status

In brief

Culinary water line project (Segments 3 and 4) appears on 2 recorded agendas, from the City Council work session meeting of February 16, 2023 to the City Council meeting of February 28, 2023.

On record, it was approved once.

The most recent decision was approved (5-0) at the City Council meeting of February 28, 2023.

Follow the money and project delivery

Culinary water line project (Segments 3 and 4)

Under construction

  1. Council action

    Approved: 18-inch culinary water line, Segment 4 construction · Approved minutes Record → · Feb. 28, 2023

  2. Money in the record

    contract: $5.68 million — 18-inch culinary water line project, Segment 4 Record → · Feb. 28, 2023

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. February 28, 2023 · City Council

    18-inch culinary water line, Segment 4 construction

    Approved · 5-0

    Added to the agenda because the contractor needed to procure materials quickly. Bid tabulation not in minutes.

    Moved by Council Member Staci Carroll, seconded by Council Member Ryan Hunter. Vote: 5-0

  2. February 16, 2023 · City Council work session

    FY2023 capital projects and budget status

    Discussed

    Station 52 to finish this summer; up to $12 million in road improvements rolled over; 200 South funded; 700 North connection geotech 95% designed; signal materials bought for 620 South 600 East; water line Segment 3 done and Segment 4 out to bid; CDBG Phase 10 funded. Building permit revenue down. Outstanding bonds: PI (2035), Art Dye and cemetery (2028), Station 52 (2038), 36-inch waterline (2041), TOD 200 South (2047); bond rating AA-. PARC awards about $1.7 million in May, including $390,000 in reserves.