400 West and 1200 South roundabout
Proposed two-lane roundabout at 1200 South and 400 West to fix projected failing traffic levels before 2040, designed with Horrocks Engineering. Presented to the council Dec. 8, 2020.
In review
- Type
- Road project
- Location
- 1200 South and 400 West, Orem
In brief
400 West and 1200 South roundabout appears on one recorded agenda: the City Council meeting of December 8, 2020.
Follow the money and project delivery
400 West and 1200 South roundabout
- Council action
No approval or denial linked in the records collected.
- Money in the record
No itemized amount linked in the records collected.
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
December 8, 2020 · City Council
1200 South and 400 West roundabout design (work session)
Discussed
City Engineer Sam Kelly said traffic at the intersection is projected to reach a failing level of service before 2040 and proposed a two-lane roundabout, designed with Horrocks Engineering, that would reach levels A and B. Council discussion covered construction impacts, landscaping, a maintenance agreement with UVU and bus rapid transit.