400 East 1600 North intersection
Redesign of an intersection crossed by the Murdock Canal Trail, funded in part by a $1.5 million MAG award. A grade-separated crossing estimated at $12 million was the preferred option, with short-term crosswalk improvements.
- Where it stands
- In review
- Type
- Road project
- Location
- 400 East and 1600 North
- Applicant
- City of Orem
Every hearing and vote
August 27, 2024 · City Council
400 East 1600 North intersection concept
Discussed
City Engineer Taggart Bowen said the intersection, crossed diagonally by Murdock Canal Trail users, received $1.5 million in MAG funding. Consultant JUB narrowed 12 options to five; the preferred choice in a social media survey was a grade-separated crossing estimated at $12 million, 5-7 years away, with directional crosswalk improvements as a short-term fix.