Pole Canyon extraction permit

DAI Land Development request to excavate about 500,000 cubic yards from 68 acres in Pole Canyon to grade for homes. Discussed in a June 2, 2020 work session; staff may approve the permit unless the council asks it to return.

In review

Type
Public project
Location
Pole Canyon
Size
68 acres
Applicant
DAI Land Development

In brief

Pole Canyon extraction permit appears on one recorded agenda: the City Council meeting of June 2, 2020.

Follow the money and project delivery

Pole Canyon extraction permit

In review

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    No itemized amount linked in the records collected.

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. June 2, 2020 · City Council

    Pole Canyon extraction permit

    Discussed

    In the work session the council heard a request from DAI Land Development to remove about half a million cubic yards of material from a 68-acre area in 11-acre increments to grade for homes within the 3,000-acre Pole Canyon development, finishing by the end of 2020. Material would stay in Pole Canyon under the master development agreement. Members raised blasting, truck routes, dust, the 4000 North realignment with UDOT, fines, nearby residents and water tanks, ridgeline grading and processing noise. The council directed engineering to address these issues and consider regulations and fines. Staff will approve the permit unless the council asks for it to return as an action item.

    • Applicant: DAI Land Development (Nate Shipp; Steve Jackson, Jackson Engineering)
    • Scope: about 500,000 cubic yards from 68 acres