Eagle Mountain · City Council

Council approves Stadion master infrastructure agreement with about $1.8 million in Meta reimbursements and a lobbyist contract

July 19, 2022, 4:00 p.m. · Eagle Mountain City Council Chambers, 1650 E Stagecoach Run, Eagle Mountain, Utah

The council voted 5-0 to approve a master infrastructure agreement with Stadion, LLC under which Meta would reimburse the city about $1.8 million for water and road work, with the booster pump completion date moved to December 31, 2022. It also approved a lobbyist services agreement with Legislative Executive Consulting, LLC, a Utah Broadband franchise and Planning Commission organization changes. The work session included a growth update showing residential permits fell from 1,609 to 1,440 in fiscal 2022.

From the approved minutes. Updated October 14, 2026.

Decisions at a glance

Agenda, item by item

  1. Item 9.C · Development

    Master infrastructure agreement, Stadion, LLC

    Approved with conditions · 5-0 · Pony Express Parkway; Cory Wride Memorial Park

    Staff said Meta would reimburse the city about $1.8 million for water infrastructure, road improvements and up to two years of staffing help, including the reuse filtration system and the Cory Wride Park booster pump station. In exchange the city would prioritize resurfacing Pony Express Parkway before December 2024, with Google covering part of that cost. Staff asked to move the booster pump completion date from October 31 to December 31, 2022. The council approved the agreement with the December 31 date; the minutes word the item both as the booster pump station and as the booster infiltration portion.

    • Payment$1.80 million to Stadion, LLC Meta reimbursement to the city for water infrastructure, road improvements and staffing help

    Moved by Council Member Brett Wright, seconded by Council Member Jared Gray. Vote: 5-0

    Follow Stadion master infrastructure agreement (Meta) in the development tracker →

    Follow Pony Express Parkway widening in the development tracker →

  2. Item 9.A · Contract

    Lobbyist services agreement, Legislative Executive Consulting, LLC

    Approved with conditions · 5-0

    The month-to-month agreement was discussed in the work session, including the termination clause, reporting and meeting frequency. The council approved it with at least four written reports a year and at least two in-person or virtual meetings.

    Moved by Council Member Carolyn Love, seconded by Council Member Colby Curtis. Vote: 5-0

  3. Item 14.A · City code

    Planning Commission organization, EMMC 17.15.030

    Approved · 5-0

    The ordinance adds an alternate Planning Commission member, sets the alternate's term and aligns appointments with other advisory boards. The public hearing (8:44 p.m.) drew no comments. The council approved it with a correction to the word "Members" in item G.

    Moved by Council Member Brett Wright, seconded by Council Member Colby Curtis. Vote: 5-0

  4. Item 9.B · Contract

    Franchise agreement, Utah Broadband

    Approved · 5-0

    Council Member Carolyn Love questioned a provision on future code changes; staff said the agreement can be amended to reflect code updates. Approved on the consent agenda.

    Moved by Council Member Carolyn Love, seconded by Council Member Jared Gray (consent agenda). Vote: 5-0

  5. Item 11.A · Roads and utilities

    Well 7 site preparation change order 1, VanCon, Inc.

    Approved · 5-0

    Solid rock required extra excavation, raising costs. The minutes give no dollar amount. Approved on the consent agenda.

    • Change orderAmount not given to VanCon, Inc. Well 7 site preparation, change order 1

    Moved by Council Member Carolyn Love, seconded by Council Member Jared Gray (consent agenda). Vote: 5-0

  6. Item 13.A · Taxes and fees

    Consolidated fee schedule for Central Water Project water purchases

    Approved · 5-0

    The resolution adjusts fees to match the city's actual costs. The related impact fee ordinance will return after staff verify the calculations. Approved on the consent agenda.

    Moved by Council Member Carolyn Love, seconded by Council Member Jared Gray (consent agenda). Vote: 5-0

  7. Item 10.A · Subdivision

    Overland Phase D, Plat 2 bond release

    Approved · 5-0

    The plat moved into warranty on the consent agenda.

    Moved by Council Member Carolyn Love, seconded by Council Member Jared Gray (consent agenda). Vote: 5-0

    Follow Overland Phase D in the development tracker →

  8. Item 1.B · Other

    Growth update (work session)

    Discussed

    Residential permits fell from 1,609 in fiscal 2021 to 1,440 in fiscal 2022, 74 percent single-family and 26 percent multifamily. A vested unit study counted 17,080 platted units and 22,746 vested units, 39,824 combined, 81 percent single-family and 19 percent multifamily.

  9. Item 1.A · Other

    City administrator update (work session)

    Discussed

    Staff reported that a concrete shortage is easing for turn lanes on Pony Express Parkway and Ranches Parkway, Well 8 bids are due at the end of August, and an emergency-only gate is installed for White Hills secondary access while the city works with UDOT on alignment and turn lanes.

What residents said

U-turns on Wride Memorial HighwayPark amenities in Sage ParkWater conservation

A Sage Park resident thanked the council for Old Airport Road funding efforts and asked for Sage Park subdivision improvements including sprinkler redesign, xeriscaping, a trail and two pickleball courts. Another resident spoke on water conservation. Council Member Gray raised safety concerns about U-turns on Wride Memorial Highway, and city engineering is contacting UDOT. Council Member Donna Burnham attended electronically and Council Member Jared Gray joined the work session remotely at 5:45 p.m.