American Fork development tracker

Egg Farm Economic Development Area

Economic development area in which developer Reed Bromley is reimbursed for infrastructure from tax increment. A 2013 second amendment set interest at 2.5%; in November 2022 Bromley asked the council to restore 5% for 2002-2013, while staff said remaining EDA capital projects face a shortfall.

In review

Type
Development agreement
Applicant
Reed Bromley
  1. Nov 1, 2022City Council work session: Egg Farm Economic Development Area reimbursement interest
  2. Mar 15, 2022City Council work session: FY2023 capital projects and RDA funds

In brief

Egg Farm Economic Development Area appears on 2 recorded agendas, from the City Council work session meeting of March 15, 2022 to the City Council work session meeting of November 1, 2022.

Follow the money and project delivery

Egg Farm Economic Development Area

In review

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    budget: $5.71 million — Requested FY2023 public works capital projects; budget: $1.78 million — 700 North connection road (design; more needed for construction); budget: $850,000 — 300 West improvements Record → · March 15, 2022

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. November 1, 2022 · City Council work session

    Egg Farm Economic Development Area reimbursement interest

    Discussed

    Reed Bromley, developer of the Egg Farm area, said the 2013 second amendment to his EDA development agreement lowered interest on his reimbursable infrastructure costs from 5% to 2.5% and asked that 5% apply from 2002 to 2013. He cited a Lewis Young Robertson & Burningham schedule line for 'excess funds for agency use.' Bunker said up-front infrastructure consumed early increment, the EDA is capped and remaining capital projects face a shortfall. Councilmember Shelton, on the council in 2013, said the amendment clearly set 2.5% for 2002-2027 and that Bromley had agreed. The mayor said staff would send capital project figures and he would talk with council members individually.

    • Developer: Reed Bromley (attorney Dan Van Woerkom present)
    • First amendment 2007; second amendment 2013
    • Developer receives share of tax increment (75% of available increment cited); 25% held for city improvements
  2. March 15, 2022 · City Council work session

    FY2023 capital projects and RDA funds

    Discussed

    Requested public works capital totaled $5,712,477, including $2.88 million for infrastructure management, $1.776 million for the 700 North connection road and $850,000 for 300 West improvements. Other requests: Fire Station 52 and police range, Fire Station 53 land, a police/courts feasibility study, and building repairs. The Egg Farm EDA has about $1.4 million for 1100 South and possibly 1500 South widening.