Elektron Solar renewable energy project

Park City's 20-year agreements with Rocky Mountain Power and PacifiCorp for the Elektron Solar Project I, approved Sept. 17, 2020, pending regulatory approval in November.

Where it stands
Approved
Type
Public project

Every hearing and vote

  1. September 17, 2020 · City Council

    Rocky Mountain Power 20-year appendix, Elektron Solar Project I

    Approved · 5-0

    The council approved the 20-year appendix to the renewable energy agreement; regulatory approval is expected in November.

    Moved by Council Member Max Doilney, seconded by Council Member Nann Worel. Vote: 5-0

  2. September 17, 2020 · City Council

    Marketing communications agreement with PacifiCorp and Elektron Solar, LLC

    Approved · 5-0

    The council approved the agreement. The minutes say regulatory approval is expected Nov. 10 while staff slides list Nov. 20.

    Moved by Council Member Tim Henney, seconded by Council Member Becca Gerber. Vote: 5-0

  3. March 3, 2023 · City Council

    Sustainability updates: renewable energy, mining soils and recycling

    Discussed

    The Elektron Solar project in Tooele County is expected to finish by year-end toward the city's goal of 100 percent renewable energy by 2030, and a joint utility agreement will be filed with the Public Service Commission. Staff will propose an ordinance amendment on legacy mining soils. Staff proposed a regional recycling facility on a 9.7-acre county-owned Gillmor parcel on Old US 40, free land with utility and road costs estimated at about $1.8 million.

  4. April 27, 2023 · City Council

    20-year appendix with Rocky Mountain Power for Elektron Solar Project I

    Approved · 5-0

    The original deadline was missed, so the appendix was restated; completion is expected by late fall.

    Moved by Council Member Becca Gerber, seconded by Council Member Jeremy Rubell. Vote: 5-0

  5. February 26, 2026 · City Council

    Utah Renewable Communities update (work session)

    Discussed

    The Elektron Solar plant serves Park City and 18 other entities. The Community Clean Energy Program awaits Public Service Commission approval; participants would see an average increase of $3 to $4 a month, residents can opt out and the city must pass an ordinance to participate. No vote.

  6. April 30, 2026 · City Council

    Community Clean Energy Program (Ordinance 2026-06)

    Approved · 3-0

    Residential participation costs $4 a month with an opt-out and no add-on for low-income customers; bill impacts are expected in early 2027. No public comment.

    Moved by Council Member Molly Miller, seconded by Council Member Bill Ciraco. Vote: 3-0; Council Members Parigian and Zegarra excused