Bonanza Park transmission line undergrounding

Burying Rocky Mountain Power transmission lines in Bonanza Park to remove an aerial easement and free land for development. Council reviewed two options in June 2024 and approved a construction agreement in July 2024.

Approved

Type
Public project
Location
Bonanza Park
  1. Sep 26, 2024City Council: FY 2025 adjusted budget (Ordinance 2024-18)
  2. Aug 15, 2024City Council: Rocky Mountain Power transmission line undergrounding agreement
  3. Jun 28, 2024City Council: Rocky Mountain Power transmission line undergrounding (work session)
  4. May 23, 2024City Council: Transmission line underground study (Rocky Mountain Power)
  5. Apr 11, 2024City Council: Rocky Mountain Power Park City to Judge wildfire mitigation project

In brief

Bonanza Park transmission line undergrounding appears on 7 recorded agendas, from the City Council meeting of September 21, 2023 to the City Council meeting of September 26, 2024.

On record, it was approved 2 times.

The most recent decision was approved (5-0) at the City Council meeting of September 26, 2024.

Follow the money and project delivery

Bonanza Park transmission line undergrounding

Approved

  1. Council action

    Approved: FY 2025 adjusted budget (Ordinance 2024-18) · Draft minutes Record → · Sept. 26, 2024

  2. Money in the record

    budget: $1.50 million — Marsac retaining wall; budget: $3.70 million — Rocky Mountain Power transmission undergrounding increase Record → · Sept. 26, 2024

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. September 26, 2024 · City Council

    FY 2025 adjusted budget (Ordinance 2024-18)

    Approved · 5-0

    The council approved the adjusted budget, including $1.5 million for the Marsac retaining wall ($500,000 Building Authority, $625,000 Main Street RDA, $375,000 China Bridge capital or parking funds), a $3.7 million increase for the Rocky Mountain Power undergrounding, and a budget-neutral merger of Housing into a Housing and Economy budget.

    Moved by Council Member Ryan Dickey, seconded by Council Member Tana Toly. Vote: 5-0

  2. August 15, 2024 · City Council

    Rocky Mountain Power transmission line undergrounding agreement

    Approved · 4-0

    The council approved a $7,077,547 construction agreement with Rocky Mountain Power to bury transmission lines in Bonanza Park, removing an aerial easement, adding cemetery plots and removing towers at Boot Hill. $3.5 million had been budgeted. Staff recommended using FY24 accrued interest; Council Member Jeremy Rubell first moved that, then withdrew and moved to authorize transient room tax (TRT) funds, which passed. Mark Fischer said undergrounding unlocks Bonanza Park and that approval of the Yarrow project is critical to its development.

    Moved by Council Member Jeremy Rubell, seconded by Council Member Ryan Dickey. Vote: 4-0; Council Member Bill Ciraco excused

  3. June 28, 2024 · City Council

    Rocky Mountain Power transmission line undergrounding (work session)

    Discussed

    In a work session with no vote, Council Members Rubell, Parigian, Ciraco and Dickey indicated support for Option A, estimated at $7,077,622, over Option B at $5,981,942. A $3.4 million placeholder was budgeted.

  4. May 23, 2024 · City Council

    Transmission line underground study (Rocky Mountain Power)

    Discussed

    Option A costs about $6.6 million and reduces visual and wildfire risk; option B costs about $5.6 million. Rubell supported option A; Dickey wanted more information and the city manager asked for cost recovery options. A decision is needed by July. Presentation only.

  5. April 11, 2024 · City Council

    Rocky Mountain Power Park City to Judge wildfire mitigation project

    Discussed

    Undergrounds the distribution circuit while transmission lines stay overhead; work runs May through October 2024 at about 150 feet a day. The mayor asked the utility to return in mid-May on Bonanza Park undergrounding. Presentation only.

  6. March 7, 2024 · City Council

    Communications: staff reports on remnant parcels, transit year-end statistics and Bonanza transmission undergrounding

    Discussed

    Rubell wanted an RFP issued before land use changes go through the Planning Commission, and Parigian agreed. No action.

  7. September 21, 2023 · City Council

    Rocky Mountain Power infrastructure near Boot Hill

    Discussed

    Phase one (about $9 million) routes the Snyderville line underground to the base of Boot Hill; phase two (about $50 million over 5 to 10 years) adds a new substation and undergrounding. A feasibility study would take up to six months and cost $300,000 to $500,000. Members expressed support for phase one and the feasibility study; Doilney hoped the utility would share costs. No vote.