Holladay skate park

City skate park by Spohn Ranch; the opening was reported in January 2022.

Approved

Type
Public project
  1. Mar 5, 2026City Council: Resolution 2026-08: interlocal agreement with Salt Lake County for the Holladay skate park
  2. Apr 11, 2024City Council: Resolution 2024-12: Interlocal agreement with Salt Lake County for TRCC park improvements
  3. Nov 16, 2023City Council: Work meeting: business advisory board, code enforcement and skate park
  4. Oct 19, 2023City Council work session: City manager and council reports
  5. Jun 15, 2023City Council work session: City manager report

In brief

Holladay skate park appears on 15 recorded agendas, from the City Council meeting of January 21, 2021 to the City Council meeting of March 5, 2026.

On record, it was approved 4 times.

The most recent decision was approved (6-0) at the City Council meeting of March 5, 2026.

Follow the money and project delivery

Holladay skate park

Approved

  1. Council action

    Approved: Resolution 2026-08: interlocal agreement with Salt Lake County for the Holladay skate park · Approved minutes Record → · March 5, 2026

  2. Money in the record

    contract: amount not given — Holladay skate park Record → · March 5, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. March 5, 2026 · City Council

    Resolution 2026-08: interlocal agreement with Salt Lake County for the Holladay skate park

    Approved · 6-0

    Interlocal agreement for the skate park.

    Moved by Council Member Emily Gray, seconded by Council Member Drew Quinn. Vote: 6-0

  2. April 11, 2024 · City Council

    Resolution 2024-12: Interlocal agreement with Salt Lake County for TRCC park improvements

    Approved · 6-0

    $125,000 in county funding with a $30,000 city match, mostly from a prior skate park lighting fundraiser. It funds sports lighting and replacing fiberglass trellis columns in City Hall Park with stone.

    Moved by Council Member Ty Brewer, seconded by Council Member Paul Fotheringham. Vote: 6-0; unanimous

  3. November 16, 2023 · City Council

    Work meeting: business advisory board, code enforcement and skate park

    Discussed

    Business advisory board introductions, administrative code enforcement, a skate park update and calendar review. No votes.

  4. October 19, 2023 · City Council work session

    City manager and council reports

    No action

    A county board approved a $120,000 application for skate park lighting and replacing fiberglass pillars with stone, with a $30,000 match raised through donations, pending county council approval.

  5. June 15, 2023 · City Council work session

    City manager report

    No action

    The city applied to Salt Lake County for $180,000 in TRCC funding for parking improvements, part of skate park lighting and replacing fiberglass pillars under the trellis. The mayor reported a county award of $5.1 million for Wasatch Boulevard improvements from 3300 South through Millcreek and that city revenue was 5% to 7% below monthly projections.

  6. April 20, 2023 · City Council

    Resolution 2023-15: Agreement with Salt Lake County for use of the Holladay skate park

    Approved · 6-0

    The county plans classes on Thursdays in June, July and August from 9 to 11 a.m., open to the public with a small fee collected by the county.

    Moved by Council Member Dan Gibbons, seconded by Council Member Drew Quinn. Vote: 6-0; unanimous

  7. September 8, 2022 · City Council

    Work meeting: skate park lighting

    Discussed

    About $41,000 has been spent on underground preparation; remaining cost is about $75,000 of a roughly $116,000 total. Council Member Brewer proposed community fundraising for $75,000 and offered a personal contribution. The council reached consensus to pursue the project, with installation targeted for next summer.

  8. August 18, 2022 · City Council work session

    Skate park lighting

    Discussed

    Advocates cited a 2021 survey in which 89.2% preferred lights. Spohn Ranch estimated $60,000 to $80,000; an advocate estimated about half that. The mayor said the main question was whether the council supported installing lights.

  9. August 11, 2022 · City Council

    Resolution 2022-22: Interlocal facilities use agreement with Salt Lake County for the skate park

    Approved · 6-0

    The county would run a Saturday skateboarding clinic from 9 a.m. to noon for seven weeks through October 8 and provided the required liability protections.

    Moved by Council Member Ty Brewer, seconded by Council Member Paul Fotheringham. Vote: 6-0; unanimous

  10. June 16, 2022 · City Council

    Work meeting: Highland Drive study and skate park concept

    Discussed

    Staff estimated construction at $21.5 million including a 30% contingency; burying utilities would cost about $8 million versus $280,000 to relocate them, and the council's sense was that burial was not feasible without other funding. A survey found 42% for a complete street alternative and 52% for a five-lane alternative with a multi-use pathway. A grant application to the Wasatch Front Regional Council is planned for fall 2022. No votes were taken.

  11. October 7, 2021 · City Council

    City manager report: 3900 South and skate park

    Pending

    Updates on the 3900 South project and the skate park.

  12. June 3, 2021 · City Council

    Work meeting: tax relief, ADUs and tentative budgets

    Pending

    Topics: tax relief programs with the county treasurer, continued ADU discussion, and the historical committee, skate park schedule, capital and stormwater funds, debt fund and parks and public works budgets.

  13. April 8, 2021 · City Council

    Work meeting: final skate park design

    Discussed

    The design has about 9,000 square feet of new concrete, an inground bowl on the east end, a linear street course on the west and a mountain-themed vertical sculpture, with groundbreaking planned for May and opening targeted for mid to late August.

  14. March 25, 2021 · City Council work session

    Review of 2020-21 goals

    Discussed

    Items noted: the Cotton Bottom sale and reopening completed; the stormwater utility fee approved after a public process; short-term rental penalties strengthened; council chambers upgraded; pickleball courts being resurfaced; skate park under design-build contract; canal trails study complete.

  15. January 21, 2021 · City Council

    Work meeting: skate park design-build selection

    Discussed

    Four proposals were received by the December 18 deadline. A selection committee including Council Members Petersen and Durham unanimously chose Spohn Ranch, which offered a two-year warranty, with partners G Brown Design and Perigee Consulting. Design starts in early February, construction late April over 12 weeks and opening mid-to-late July. No contract amount is stated.