Friday, October 16, 2026The Utah Ledger

Everything Utah, every day.

Holladay · City Council

Holladay council approves cell tower lease amendment and justice court recertification; budget amendment hearing draws no comment

November 16, 2023, 6:00 p.m. · City Council Chambers, 4580 South 2300 East, Holladay

The council voted 6-0 to approve a third amendment to a cell tower lease and to recertify the Holladay Justice Court. A public hearing on 2023-24 budget amendments had no comments. A work meeting reviewed those amendments, including $905,000 from capital projects fund balance and a $480,000 match for a $6.7 million federal grant for the Highland Drive bridge. The minutes record the mayor voting with the council members, so tallies include him.

From the approved minutes. Updated October 14, 2026.

Decisions at a glance

Agenda, item by item

  1. Item V · Contract

    Resolution 2023-32: Third amendment to cell tower lease with CCTM1, LLC

    Approved · 6-0

    Amends the lease. The minutes give no amount.

    • ContractAmount not given to CCTM1, LLC Third amendment to cell tower lease

    Moved by Council Member Drew Quinn, seconded by Council Member Dan Gibbons. Vote: 6-0; unanimous

  2. Item VI · Other

    Resolution 2023-33: Recertify the Holladay Justice Court

    Approved · 6-0

    Recertifies the city justice court.

    Moved by Council Member Dan Gibbons, seconded by Council Member Matt Durham. Vote: 6-0; unanimous

  3. Item IV · Budget

    Public hearing and work meeting discussion: 2023-24 budget amendments

    Discussed

    Amendments include $905,000 from capital projects fund balance for multiple expenses, $100,000 for Spring Lane park concept design and public engagement, a $200,000 transfer as a match for a 2700 East sidewalk grant, and a $250,000 match for the $600,000 historic experience grant. A $6.7 million federal grant for the Cottonwood Creek bridge on Highland Drive requires a Holladay match of $480,000 (6.77% of project cost, which rose from $3.5 million to $7 million). Historic signs would cost about $5,000 each rather than about $300. The capital projects fund fell from $14.7 million to about $11 million after an RDA loan.

    • Budget$905,000 Capital projects fund balance for multiple expenses. Paid from Capital projects fund balance
    • Grant$480,000 Holladay match for $6.7 million federal grant for the Highland Drive bridge. Paid from City funds
    • Budget$200,000 Match for 2700 East sidewalk grant. Paid from Capital projects fund

    Follow Highland Drive bridge over Big Cottonwood Creek in the development tracker →

    Follow Spring Lane Elementary site in the development tracker →

  4. Other

    Work meeting: business advisory board, code enforcement and skate park

    Discussed

    Business advisory board introductions, administrative code enforcement, a skate park update and calendar review. No votes.

    Follow Holladay skate park in the development tracker →

What residents said

None.