Holladay development tracker

City Hall renovation and seismic upgrade

City Hall renovation estimated at $7.9 million, about $10.4 million with contingency and relocation; a congressional earmark was reduced from $2 million to $1.7 million and bond options are being modeled for early 2025.

Where it stands
In review
Type
Public project

Every hearing and vote

  1. January 11, 2024 · City Council work session

    Review of 2023 retreat goals

    Discussed

    The six priorities were police services, Spring Lane, affordable housing, City Hall renovation, stormwater and roads. A 2023 accomplishments summary will be published and the 2024 retreat is set for February 29.

  2. February 15, 2024 · City Council

    Work meeting: City Hall seismic options

    Discussed

    Seismic renovation with upgrades was estimated at $350 to $400 per square foot, versus $10 to $15 per square foot for full demolition. Council Member Gray reported recycling truck damage of over $100,000.

  3. April 25, 2024 · City Council

    Work meeting: City Hall seismic presentation

    Discussed

    The council was briefed on the Level Two seismic option, renovation phases and funding timing. About $80,000 was estimated for replacing the City Hall water cooling system. Juneteenth will be observed on the Monday of the holiday week, aligning with the state.

  4. May 9, 2024 · City Council work session

    Discussion on the tentative budget

    Discussed

    Property and sales tax make up about 80% of general fund revenue; police is about 35% of expenses and fire about 14%. The tentative budget includes a 15% property tax increase generating about $1.1 million and a 4% cost-of-living adjustment; Council Member Fotheringham suggested increases about every three years. The county public works contract rose about 5% (about $150,000). The stormwater fund collects about $1 million a year with no fee increase proposed. About $350,000 is budgeted for City Hall design, $30,000 for bus shelters and $35,000 for sealing two playground surfaces. Year-end fund balance is $7.6 million, of which $1.8 million is restricted; the council goal is to keep it at or above 20%.

  5. June 6, 2024 · City Council

    City manager report: finances and City Hall earmark

    No action

    Through May, property tax and sales tax were each about $100,000 below budget and franchise taxes were expected to exceed budget by about $150,000. Representative John Curtis's office indicated a $2 million earmark for City Hall seismic work, about 20 to 25% of project cost.

  6. July 11, 2024 · City Council

    City manager report: grants

    No action

    A federal resilience grant for City Hall seismic work did not advance. A congressional earmark was reduced from $2 million to $1.7 million, with construction possibly beginning in January 2026. A $100,000 state safe sidewalk grant requires a match.

  7. November 7, 2024 · City Council

    Work meeting: options for funding Spring Lane and City Hall

    Discussed

    The bond adviser said City Hall is estimated at $7.9 million, with about $1 million of exclusions such as HVAC, for a project total of about $10.4 million including a $1 million contingency and about $600,000 for relocation. The Spring Lane park is estimated at $7.5 million in most scenarios. One scenario is a $4 million bond using a $1.7 million earmark, ARPA funds, $7.7 million from capital projects and $1.5 million of fund balance. Council Member Fotheringham said fund balance should be preserved for roads and storm drains. Staff will run more scenarios for early 2025.