Wastewater system improvements and revenue bonds

The council authorized issuing up to $37,000,000 in wastewater revenue bonds on Nov. 19, 2024 to finance construction improvements to the city's sewer infrastructure.

Where it stands
Approved
Type
Public project
Location
Provo sewer system

Every hearing and vote

  1. November 5, 2024 · City Council work session

    Wastewater project financial update

    Discussed

    Presentation of a financial update on the wastewater project. Presentation only; final approval to come later.

  2. November 19, 2024 · City Council

    Public hearing on up to $37 million in wastewater revenue bonds

    Discussed

    A public hearing was held on issuing up to $37,000,000 of wastewater revenue bonds to finance construction improvements to the city's sewer infrastructure. The Summary records hearing only.

  3. November 19, 2024 · City Council

    Wastewater revenue bond issuance

    Approved · 7-0

    A resolution authorized issuing the wastewater revenue bonds, executing supplemental indentures and other required documents, and taking necessary actions.