Orem 2000 S storm drain interlocal agreement

Interlocal agreement between Provo and Orem on funding the Orem 2000 S storm drain project. Approved 4-0 on Aug. 11, 2026.

Approved

Type
Public project
Location
Orem 2000 S
  1. Aug 11, 2026City Council: Provo-Orem interlocal agreement on Orem 2000 S storm drain
  2. Jul 14, 2026City Council work session: Interlocal agreement with Orem on the 2000 North storm drain project (26-056)

In brief

Orem 2000 S storm drain interlocal agreement appears on 2 recorded agendas, from the City Council work session meeting of July 14, 2026 to the City Council meeting of August 11, 2026.

On record, it was approved once.

The most recent decision was approved (4-0) at the City Council meeting of August 11, 2026.

Follow the money and project delivery

Orem 2000 S storm drain interlocal agreement

Approved

  1. Council action

    Approved: Provo-Orem interlocal agreement on Orem 2000 S storm drain · Agenda and reports Record → · Aug. 11, 2026

  2. Money in the record

    contract: $16,520.49 — Provo share of the 2000 North storm drain: sump connection, asphalt replacement, mobilization, traffic control and SWPPP Record → · July 14, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. August 11, 2026 · City Council

    Provo-Orem interlocal agreement on Orem 2000 S storm drain

    Approved · 4-0

    The council approved an interlocal agreement with Orem on funding the Orem 2000 S storm drain project and authorized the mayor to sign it.

    Vote: 4-0; Council Members MacKay, Christensen and Whipple excused

  2. July 14, 2026 · City Council work session

    Interlocal agreement with Orem on the 2000 North storm drain project (26-056)

    Discussed

    Engineer Danielle Nixon said Orem awarded the construction contract to RV Construction and will own the main line while Provo takes responsibility for inlets and laterals. Provo's total cost is $16,520.49. Councilor Whitlock said it appeared favorable to Provo.