Water reuse project at the Water Reclamation Facility

Project to treat wastewater to Type I reuse levels for irrigation and to add cloth filtration that removes phosphorus before release to Utah Lake. The council toured it May 16, 2023.

Where it stands
Under construction
Type
Public project
Location
Orem Water Reclamation Facility

Every hearing and vote

  1. May 16, 2023 · City Council

    Water reuse project and FrontRunner station tours (work session)

    Discussed

    The council and Planning Commission members toured the Orem Water Reclamation Facility's water reuse project, led by Assistant Public Works Director Reed Price. The project will let the plant treat wastewater to Type I reuse levels for irrigation and use cloth filtration to remove phosphorus before release to Utah Lake. They also toured the FrontRunner station, where consultant Christie Oostema of People+Place discussed station area plan possibilities and a UTA regional general manager discussed expansion plans.