Water reuse project at the Water Reclamation Facility

Project to treat wastewater to Type I reuse levels for irrigation and to add cloth filtration that removes phosphorus before release to Utah Lake. The council toured it May 16, 2023.

Under construction

Type
Public project
Location
Orem Water Reclamation Facility

In brief

Water reuse project at the Water Reclamation Facility appears on one recorded agenda: the City Council meeting of May 16, 2023.

Follow the money and project delivery

Water reuse project at the Water Reclamation Facility

Under construction

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    No itemized amount linked in the records collected.

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. May 16, 2023 · City Council

    Water reuse project and FrontRunner station tours (work session)

    Discussed

    The council and Planning Commission members toured the Orem Water Reclamation Facility's water reuse project, led by Assistant Public Works Director Reed Price. The project will let the plant treat wastewater to Type I reuse levels for irrigation and use cloth filtration to remove phosphorus before release to Utah Lake. They also toured the FrontRunner station, where consultant Christie Oostema of People+Place discussed station area plan possibilities and a UTA regional general manager discussed expansion plans.